Construction is moving quickly on a new eight-story hotel taking shape southeast of 10th and Harney Street, wedged between Omaha’s Old Market and the RiverFront. Much of the site preparation work is now done, and crews have started drilling for pilings, with a tower crane expected to go up soon.

The project is the Drury Plaza Hotel, and according to Grow Omaha, the eight-story building will have 210 rooms. Grow Omaha reports the cost at $54 million, while an earlier Grow Omaha report on the proposal from June described it as a $55 million project with 2,000 square feet of conference space, a pool, and an onsite restaurant and bar. The two figures come from different stages of reporting on the same project, and neither account in the record resolves which number is current.

Parking plans have shifted in the telling as well. The November report describes an attached parking garage with 160 spaces, while the earlier account described the proposal as an eight-story building over a two-level, 175-space garage. Drury is building on what had been a previously undeveloped grassy area between Embassy Suites and the Brickline building, placing the new hotel squarely between the Old Market and the RiverFront.

What Guests and Diners Can Expect

Once finished, the hotel is planned to include a restaurant run by a third party along with a bar open to the public, the same report notes. A separate breakfast area will be reserved for hotel guests only. The developer anticipates the project will create 65 new permanent jobs, according to the same account.

A Bumpy Road to Approval

Getting to this point wasn’t straightforward. Grow Omaha’s earlier report detailed how the Omaha Planning Board voted 4-1 to uphold a recommendation denying the hotel’s tax-increment financing and Enhanced Employment Area applications, citing a 2018 city-adopted recommendation that had identified an oversaturation of hotels in the downtown market below the luxury or upper-upscale categories.

Despite that planning board denial, the Omaha City Council ultimately sided with the developer. In August, the council voted 7-0 to approve both the project and its tax incentive, securing some written guarantees from the hotel developer in the process, as reported by WOWT.

A Crowded Downtown Hotel Market

The Drury project lands in a downtown lodging scene that has been expanding fast. A 2016 report from the Omaha World-Herald found that within a few years, downtown Omaha alone could have 19 hotels with 3,500 rooms, roughly a third more than the 15 downtown hotels then in operation. That kind of growth is part of the downtown lodging picture; the planning board had earlier raised concerns about oversaturation, even as the city council chose to move forward anyway.

For now, the most visible sign of progress is on the ground: pilings being drilled into what was once an empty grassy lot, with a crane poised to join the skyline soon. No opening date or construction timeline beyond that has been made public.