Drivers along Sierra Madre Boulevard are about to hit some slowdowns. Pasadena officials have confirmed that construction on the Sierra Madre Boulevard Median Enhancement Project is set to begin Monday, kicking off a months-long overhaul of roughly 1.25 miles of medians between Michillinda Avenue and East Washington Boulevard.
The $6.8 million construction effort is funded through Caltrans, with design work supported by the city's Measure W Local Return funds, according to the City of Pasadena. The project brings new landscaping, enhanced street lighting and a suite of green infrastructure upgrades to the busy corridor, which the city's preliminary design report once pegged at carrying roughly 16,900 vehicles a day.
Those green infrastructure elements include bioswales, bioretention areas, rock swales and subsurface drywells, all designed to capture, treat and infiltrate stormwater runoff before it leaves the corridor. The system is also meant to treat dry-weather flows from the Sierra Madre Villa and New York storm drains, diverting surface flows for treatment and irrigation use. A new, efficient irrigation system is planned as well, intended to help new plantings take root while keeping long-term water use down, per the city's announcement.
Lane Closures Expected Into Next Summer
City officials say construction is anticipated to continue through June 2027, though the work will pause for a holiday moratorium from December 15 through January 8, giving drivers a brief reprieve over the winter break. The project is phased specifically to minimize disruptions along the corridor, the city says, but motorists should still expect temporary lane closures and minor traffic delays throughout construction. Traffic control plans call for closing inside lanes in both directions, with one westbound lane and one eastbound lane affected at a time, according to the city's announcement reported by NBC Los Angeles.
How Many Trees Are Coming Down?
The project's tree removal numbers have shifted depending on the source and the stage of planning. A preliminary design report from Pasadena's Public Works department, completed in April 2024, found that of 114 trees surveyed within the medians, 50 were flagged for removal, eight required pruning and four needed additional inspection. A later account of the City Council-approved plan, published by ColoradoBoulevard.net, put the number at 44 mature trees slated for removal, with those trees to be replaced by more than 700 new plantings. The discrepancy between the two figures has not been publicly explained.
The project's budget and timeline have also moved several times since planning began. The same preliminary design report estimated total construction costs at $5,715,239 for its recommended configuration, well below the $6.8 million figure the city now cites, and noted that costs could shift as design advanced. Annual operations and maintenance for the system were estimated at $48,000 in that same report.
Timing estimates have shifted too. A December 2024 report from Pasadena Now said construction was scheduled to begin in summer 2025, while a 2026 account from ColoradoBoulevard.net pushed that expectation to late summer 2026. Construction is now set to begin Monday, November 23, 2026, months after either of those earlier projections.