The University of Houston is planning a $4 million makeover of the RAD Center, the two-story dining hub at 3457 Cullen Blvd. Level 2 is in line for a 5,600-square-foot interior buildout, with construction expected to start after the spring semester, run mostly over the summer and wrap up in August 2027.

That schedule comes from a state filing, Chron reported. The UH Board of Regents approved the $4 million project in May 2024. The budget covers design, construction, furniture, fixtures and equipment, and Perkins & Will is the listed design firm. The renovation is also described as part of the university's centennial construction work. UH reaches its 100th anniversary in March 2027.

What the Second Floor Is Supposed to Get

The buildout is meant to expand student dining and seating and add a faculty café and lounge, a multipurpose meeting room, reflection space and administrative support areas. Seating is expected to grow. The center now has 400 guest seats, including outdoor patio seating on both floors, according to the university's dining page. No confirmed count of new seats is attached to this $4 million scope.

The same page says Phase II is complete and all six food concepts are open. Options at the RAD Center include Absurd Bird, Paper Lantern, The Burger Joint, Katz Coffee and The Taco Stand.

A Final Phase With Several Calendars

May 2024 is not a fresh decision. The regents signed off on the money more than two years ago, around the time the building was only partly open. The current filing still has the hammers waiting until after spring, then squeezing most of the work into a summer that ends in August 2027.

Earlier public descriptions of a third and final phase used other calendars, and the record does not establish that those descriptions covered exactly this scope. In August 2024, The Daily Cougar reported that the phase was planned to start in summer 2025 and finish by the opening of the fall 2025 semester. That account also said the work would move the Cougar Card office and the Auxiliary Services Administrative office into the RAD Center, and add a reflection room, a satellite delivery-services office and a multipurpose room seating up to 60 people.

A university dining page later put the third and final phase in summer 2026 and said it would create more dining space and about 200 additional seats. Summer 2026 has come and gone. The schedule now on the record is the state filing's: after the spring semester, mostly over the summer, done in August 2027.

The Building Under the Upgrade

The RAD Center is a 56,000-square-foot facility. A university feature has described the open building as a $44 million project. Against that price, the new work is a $4 million interior job on a floor that already exists.

It replaced the former underground Student Center Satellite. Perkins&Will says the center took the place of a flood-prone underground dining facility that was severely damaged during Hurricane Harvey.

The opening itself came in pieces. The university says Phase I opened in spring 2024. The Daily Cougar reported a partial debut in May 2024, when students initially had access to the Nook Cafe and the RAD Market, a second phase that officially opened in September 2024, and a full opening in time for the fall 2024 semester.

The Anniversary Arrives First

March 2027 is the centennial. August 2027 is the month this buildout is expected to finish. If that filing holds, the 100th anniversary lands while the second-floor dining expansion, faculty lounge, meeting room and reflection space are still a summer construction job rather than finished rooms.

For students, the practical date is the one after another school year: expanded seating, if the project stays on this schedule, shows up at the end of summer 2027, not in time for the anniversary events five months earlier.