Everett Stunner as Boeing Chops Up Early 777X Jet

AI Assisted Icon
Published on July 20, 2026
Everett Stunner as Boeing Chops Up Early 777X JetSource: Google Street View

One of Boeing's earliest 777X airframes has been quietly chopped up in Everett, a sign of just how bumpy the road remains for the long‑delayed widebody program.

The company confirmed Sunday that a partially built 777‑9 was disassembled and recycled, with the cost of the scrapped jet already baked into previous financial statements. The move comes as Boeing wrestles with rework, certification demands, and mounting cost pressure on its flagship twin‑engine jet.

Boeing Pins Fixes on "Change‑Incorporation" and a Dedicated Rework Crew

According to The Seattle Times, a Boeing spokesperson confirmed the partially assembled airplane was taken apart for recycling and that the financial hit had already been accounted for. The Times reported that executives are reshuffling production work in Everett to keep up with the sheer volume of repairs and updates the 777X fleet now requires.

Stephanie Pope, who leads Boeing Commercial Airplanes, told The Seattle Times she "felt really good" about a new "change‑incorporation" program meant to bring those early 777X airframes up to the latest production standard. Boeing plans to assign a separate team at Everett to handle that rework, effectively creating a parallel repair line alongside standard 777X production.

Dozens of Jets and a Multi‑Billion‑Dollar Charge

Company leaders say roughly 30 777X airframes will cycle through the change‑incorporation process. The financial pain is already visible: Boeing recorded a $4.9 billion pre‑tax charge related to the 777X program in 2025 and pushed the first delivery target into 2027. Those figures were laid out in Boeing's third‑quarter 2025 results, which highlighted the accounting impact of the updated certification schedule.

Airframe WH007's Long, Slow Fade

Industry newsletter The Air Current traced the fate of the specific jet at issue, tagged WH007. The aircraft had been parked near Paine Field since 2019 before quietly vanishing and then being dismantled. The outlet cast the teardown as part of a "massive" rework challenge as Boeing trims back its pre‑certification builds and focuses on bringing a smaller, more manageable fleet up to final standard.

For Everett and the wider Puget Sound aerospace ecosystem, the scrapped airframe is a very physical reminder of how certification delays ripple outward into factory jobs, simulator work, and local suppliers. Hoodline's March coverage clears training hurdle while flagging the same regional stakes, including knock‑on effects on hiring, training approvals, and nearby manufacturers.

Boeing insists its test program is moving ahead and that it still expects the first 777‑9 delivery in 2027. Even so, the decision to break down and recycle an early airframe underscores the tangible cost of stabilizing production. Industry observers, including The Air Current, warn the rework effort will run for years and could throw fresh curveballs at supplier schedules and airline delivery plans.