Ten years after Hurricane Matthew dumped up to 14 inches of rain on Virginia Beach and left hundreds of homes damaged, the city has broken ground on a $127 million pump station where Thalia Creek meets Lake Windsor — a project officials say won't be finished until 2031. The new station is designed to replace the temporary pumps that have sat atop the Windsor Woods Tide Gate since it was completed, and it's meant to protect three neighborhoods that took some of the hardest hits back in October 2016.

The pump station will help prevent flooding in the Windsor Woods, Princess Anne Plaza and The Lakes communities, according to WAVY.com. Those same neighborhoods, along with Ashville Park, were among the areas that reported flood damage after Matthew, when approximately 800 homes were affected citywide, according to city presentations from that time. Once complete, the new station is expected to pump down Lake Windsor in less than 24 hours — a dramatic improvement over current capacity.

L.J. Hansen, Virginia Beach's director of public works, has said the city is among the most proactive communities when it comes to tackling flood threats, crediting the ability to visit other communities and borrow from their flood-prevention playbooks. The Windsor Woods Tide Gate itself — the first major project to come out of the city's broader flood protection program — is already finished, a $21.2 million structure built to create extra stormwater storage in Lake Windsor, the station reported.

A Decade of Rising Costs and Growing Ambitions

The scope of Virginia Beach's flood fight has ballooned since voters first signed off on it. In November 2021, nearly 73% of Virginia Beach voters approved a referendum allowing the city to borrow $567.5 million, alongside an up-to-four-cent increase in the real estate tax rate, to fund 21 flood protection projects originally expected to wrap up in six to seven years. Virginia Beach's city council made flood prevention a top priority in the wake of that vote.

Since then, the price tag has nearly tripled in some estimates. The Virginia Beach-area reporting now puts the cost of planned projects at $1.5 billion, while the same report notes the city has received $73 million in state and federal grants and has spent $215 million so far on planned resiliency work, per The Virginian-Pilot. Other estimates have put the total closer to $1.1 billion, with project costs rising 30% to 35% since they were first priced in 2019 and 2020 — increases the city has attributed to inflation, workforce shortages and permitting processes that have made the entire flood-prevention itinerary difficult to execute on schedule.

The broader flood protection program spans seven master project areas and roughly 30 individual projects, according to earlier Virginian-Pilot reporting. The pump station now underway is part of a specific $518 million, seven-project bundle known as the Windsor Woods, Princess Anne Plaza and The Lakes Stormwater Improvements mega-bundle, as described by Engineering News-Record. That trade publication also reports the Windsor Woods Pump Station is designed with a capacity of 432,000 gallons per minute. Virginia Beach plans to cover the cost of that mega-bundle itself.

More Pump Stations Planned Citywide

Windsor Woods isn't an isolated effort. Pump stations have already been built in Sherwood Lakes and Ashville Park since Hurricane Matthew, and the Virginian-Pilot reports the city intends to build 10 more pump stations over the next five years. Progress has also come through less flashy means — converting a golf course into a park with stormwater storage and performing extensive storm drain upgrades alongside the tidal gate construction, the outlet notes, even as more work remains.

The stakes for finishing that work are significant. Without additional mitigation, annualized flood losses in Virginia Beach are projected to climb from about $75 million today to $350 million by 2060, according to the station's reporting. A federal permitting notice from the Norfolk District of the U.S. Army Corps of Engineers confirms the Windsor Woods project includes construction of a tide gate across Thalia Creek at its confluence with Lake Windsor, along with an interim pump station — details that match the project description on the City of Virginia Beach's own stormwater program page.

For residents of Windsor Woods, Princess Anne Plaza and The Lakes, the 2031 completion date means years more of living with temporary pumps atop the tide gate before the permanent station takes over. As Virginia Beach continues flood-prevention work a decade after Hurricane Matthew, the gap between what's finished and what's still funded, permitted or under construction remains the defining tension of the effort.