Anaheim's City Council voted 6-1 on Tuesday to set a July 31, 2027 deadline for the developer behind the long-stalled A-Town housing project to fix its compliance problems or risk losing its development agreement altogether. The vote came after city staff concluded the developer, PT Metro, LLC, had fallen behind on a key construction milestone tied to the sprawling mixed-use project along Katella Avenue in the city's Platinum Triangle district.
According to the Daily Titan, Anaheim Mayor Ashleigh Aitken was the lone no vote, pushing back against giving the developer more runway given what she described as a history of inaction on the project. The council held a required public hearing before setting the termination date, and city staff — Heather Allen, Lisandro Orozco and Leonie Mulvihill — presented the recommendation that led to the deadline, the Daily Titan reported.
A-Town was first approved back in October 2005 as a multifamily residential community and mixed-use project, and it has since become one of the more closely watched developments in the Platinum Triangle, the area around Angel Stadium that also includes the Honda Center and the Grove of Anaheim, per the Daily Titan's reporting. City records describe the roughly 43.1-acre site, located at 1404 East Katella Avenue, as sitting west of State College Boulevard between Katella Avenue and Gene Autry Way, according to City of Anaheim meeting minutes from October 2015.
A Decade of Redesigns and Missed Deadlines
Anaheim revised A-Town's development plan in October 2015 to allow for up to 1,746 residential units, 50,000 square feet of commercial space and two public parks, the Daily Titan reported. The same city minutes note that the applicant at the time cited changes in the housing market and economic conditions as the reason for scaling back density from an earlier approval that had called for high-rise residential towers, and that the revised plan included public park space and a reconfigured connector-street network.
The project appeared to be moving steadily for a while. In May 2018, the council approved an amendment modifying performance milestones due in 2020, 2022, 2025 and 2030, and per the Daily Titan, A-Town went on to complete both the 2020 and 2022 milestones before the agreement was extended through October 2025.
The trouble came with the third milestone, which required construction of 462 additional residential units. The Daily Titan reported that PT Metro did not pursue building permits covering the remaining units tied to that milestone, and the council concluded in December 2025 that the developer was not in compliance. A-Town currently has 132 units outstanding, according to the Daily Titan's reporting — though the city's own February 2026 status report put total progress at 638 completed units and 330 under construction, out of a plan allowing for 1,400 to 1,746 homes, per a City of Anaheim status document.
Financing Trouble and a Request for More Time
Finalized site plans cover A-Town's remaining Areas B, C and D, and those areas have experienced difficulty financing large-scale mixed-use podium projects, per Heather Allen as cited by the Daily Titan. PT Metro requested additional time in 2025 to pursue amendments to the revised agreement and master site plan, the outlet reported.
City records show the council held a required public hearing in January 2026 to establish a 10th-anniversary milestone date of July 31, 2026. A City of Anaheim legal notice from that period confirms the council was set to consider establishing new development timeframes for PT Metro, LLC at a hearing scheduled for January 27, 2026. According to the Daily Titan, the council then directed city staff to either modify or terminate the agreement at a noticed public hearing within 45 days after notice is provided — a process that led to Tuesday's vote. Allen told the council staff recommended adopting the resolution, and said staff would return with an ordinance to terminate the revised agreement if the amendment isn't completed by July 2027, the Daily Titan reported.
Affordable Housing Questions and a Dissenting Vote
The vote drew pointed questions about fairness and enforcement. Marc Herbert, who runs an Anaheim watchdog blog, said affordable housing is the city's number one problem and that the city's actions haven't matched its stated concern, according to the Daily Titan. Herbert argued affordable housing should be the top consideration both for A-Town and for the property across the street.
Aitken asked whether A-Town's developer is exempt from increased in-lieu fees and affordable housing ordinances that have taken effect since the project's approval. Allen clarified that those increased fees and housing ordinances would not apply to the developer unless they were incorporated directly into the agreement, the Daily Titan reported. Aitken went on to express doubt about the project's progress given what she called the developer's history of inaction, predicting the council would be back in July 2027 with no movement on the project, and urging the city to stop letting developers extend agreements far into the future without meeting benchmarks along the way.
Under California Government Code Section 65868, a development agreement may be amended or canceled, in whole or in part, by mutual consent of the parties or their successors in interest, with notice of intention given in the manner required by state law — the legal framework governing how Anaheim and PT Metro could still revise the A-Town agreement before the new deadline.
A Pattern Across the Platinum Triangle
A-Town isn't the only ambitious Platinum Triangle project to hit turbulence. The council approved developer LT Global's proposed LT Platinum Center in 2016 for a 14.8-acre site near Angel Stadium, envisioned with 400 apartments, a 200-key hotel, 430,000 square feet of retail and entertainment space, 75,000 square feet of offices and a 1.5-acre park, according to Bisnow. That project never materialized as planned — Bisnow reported LT Global later sold nearly 15 acres intended for the development to Anaheim Jianyong Investment for $32 million, with the property eventually passing to PDC Anaheim Properties. A new owner, Camphor Properties, has said it's planning a smaller mixed-use development there with a hotel, grocery and residential component, though not on the scale of LT Global's original vision.