Nearly 100 homes in Ann Arbor's Veridian at County Farm neighborhood are about to become Michigan's first residential virtual power plant, with DTE Energy gaining remote control of a network of home batteries that can feed stored solar power back onto the grid when needed. The Michigan Public Service Commission approved the two-year pilot, and Veridian households could enroll in the coming weeks, according to the Michigan Advance.
A State Regulator Signs Off On A New Grid Tool
The Michigan Public Service Commission's September 10 order found that the proposed Residential Battery VPP pilot program “should be approved,” clearing the way for DTE Electric to move forward, according to the Michigan Public Service Commission. DTE Energy and battery maker sonnen formally announced the launch on October 29, describing it as Michigan's first residential battery virtual power plant pilot, per DTE Energy. The commission's order says DTE plans to draw on up to 100 Veridian residential batteries, while DTE's own announcement described nearly 100 homes participating.
Sonnen USA manufactures the home storage systems installed at Veridian and is helping operate the pilot alongside DTE using proprietary software, according to the Michigan Advance. The commission's order specifies that the standard sonnen battery installed in Veridian homes provides 4.8 kilowatts of power along with 20 kilowatt-hours of energy storage. Together, the fleet is expected to deliver up to about 300 kilowatts for three hours, according to Canary Media.
What Veridian Looks Like On The Ground
The Michigan Public Service Commission calls Veridian at County Farm a net-zero community in Ann Arbor; DTE describes it as fossil-fuel-free, with solar and batteries. DTE describes the community as sitting on 14 acres adjacent to County Farm Park, featuring 170 mixed-income homes built to be fossil fuel-free. As of Canary Media's reporting, 44 market-rate homes with solar and batteries had been built out of 120 planned, along with 50 affordable housing units that don't yet have batteries.
The idea for turning Veridian into a grid resource goes back further than the recent regulatory approval. Matt Grocoff, founder of Thrive Collaborative, began considering a virtual power plant pilot at Veridian back in 2019, per the Michigan Advance. Geoff Ferrell described Veridian as a test bed for the pilot, the outlet reports, and Grocoff said the project is now drawing calls from developers and utilities across the country, including interest from a project called Peace Hill in Townsend, Washington.
The Money: What DTE Will Pay, And What's Still Unclear
Mitch Hall said DTE will pay participating residents to take part in the pilot, according to the Michigan Advance. The commission's order lays out a performance-based incentive of $105 per kW-year, with a maximum total incentive value of $504 per battery. Still, exact figures on how much individual customers would be compensated weren't available to Canary Media before that outlet's report published, and DTE did not respond to its request in time.
The commission's order estimates the overall program costs for the two-year pilot at $500,000, with DTE Electric expecting the pilot to launch late in the fourth quarter of 2026. Commission staff must also convene a workgroup within 120 days of the pilot's launch to weigh improvements ahead of year two.
Why DTE Sees A Cheaper Path To Reliability
DTE CEO Joi Harris said the pilot “is an opportunity to test an approach that could ultimately provide a lower-cost way to meet growing energy needs and strengthen reliability,” according to DTE Energy. Virtual power plants in general can reduce demand peaks and lessen a utility's need for costly grid upgrades and fossil-fuel peaker plants, the Michigan Advance reports.
The stakes extend beyond one Ann Arbor subdivision. Michigan had no full-scale virtual power plants as of December 2025, according to regulators and experts cited by MLive, even as a federal report found such programs could be more than 40% cheaper than traditional grid investments and rolled out in months.
How Veridian Compares To Programs Elsewhere
Nationally, the Department of Energy estimated virtual power plant capacity at roughly 30 gigawatts in 2025, or less than 4% of peak demand.
Similar programs exist elsewhere. MLive has reported on a Utah battery program.