Bethel's Toronto Reservoir Could Stay Drawn Down Until 2030

AI Assisted Icon
Published on November 16, 2026
Bethel's Toronto Reservoir Could Stay Drawn Down Until 2030Reservoir Shoreline
Sikes Photos / Unsplash

Toronto Reservoir in Bethel has been held well below the shoreline Sullivan County neighbors used for years, and the earliest anyone is talking about water coming back is 2030.

Eagle Creek, which operates the dam, has kept the reservoir down since 2023 because of seepage that could signal a safety problem, WAMC reported. Residents who asked not to be named told the station the water sits about 25 feet lower than it used to. Local recreation has been off the table since the drop.

How The Level Came Down

The company's operating update puts a date on the start. EC Mongaup began drawing down Toronto Reservoir on May 12, 2023, after FERC's Division of Dam Safety and Inspections directed a controlled lowering of about half a foot a day, Eagle Creek Renewable Energy says. EC Mongaup agreed to keep the reservoir at or below 1,200 feet above sea level until dam remediation is complete.

That cap sits about 15 feet under typical recreation levels, WAMC reported. Waterfront residents, separately, described a drop of about 25 feet below normal over the summer. Those are different reference points, not two readings of the same gauge.

The dam is an earthen structure, roughly a century old, built of natural materials that allow some seepage. Muddy seepage was a different signal: possible erosion, and danger. Mid Hudson News reported that the seepage is what led FERC to order the lower level. WAMC's account says Eagle Creek tried a series of fixes that did not work.

A Longer Haul For Fire Trucks

The White Lake Fire Company says neither it nor the Smallwood Fire District can draw firefighting water from the reservoir now. Commissioner Brendan Cunningham, the company's former chief, said the low water left no access points. Crews have to go elsewhere, which takes time.

He put a local number on the delay. A fire in Chapin Estates took about 15 to 20 minutes to reach from the White Lake firehouse. Cunningham also said a fire doubles in size every 30 seconds. Extra miles are not an abstract inconvenience in that math.

Congressman Josh Riley has taken up the same worry. He said first responders are concerned about answering fires at the current level, and that the low water threatens the town tax base.

What The Shoreline Lost

Before the drawdown, swimmers had a spot they called Treasure Island. The reservoir supported herons, bald eagles and fish. Since the water came down, WAMC reported, it has not been usable for local recreation.

On Nov. 11, Riley said the drawdown "has jeopardized public safety, eroded the local tax base, compromised the environment, and deprived sportsmen and families of recreational opportunities," Mid Hudson News reported.

Hal Teitelbaum, a full-time waterfront resident and president of Homeowners on Toronto, said weather and other delays prolonged the repair process. The group is a civic association that stewards the reservoir. His account of the wait sits next to the company's, which is about investigations and reviews rather than the weather.

A Schedule That Still Ends In Testing

None of the public timelines is a confirmed completion date. Eagle Creek told a resident it would not begin construction until late 2027, The River Reporter reported, and attributed that pace to carefully engineered investigations and required federal and state regulatory reviews.

The same paper reported that Eagle Creek Hydropower told residents repairs would continue until 2029, with testing in 2030 and water returning that year at the earliest. WAMC's shorter version is that the dam might not be repaired until 2030.

In August, State Assemblywoman Paula Kay and Riley urged FERC, Eagle Creek Hydropower and the parent company to start the work. Kay said the company had not authorized the initial engineering needed to decide next steps, even while estimating completion in 2030, Mid Hudson News reported. WAMC reported that Apollo Global Management acquired Eagle Creek in 2025.

Pressure, And A Town That Cannot Order The Water Back

Riley told WAMC he is trying to get Eagle Creek, FERC and Apollo Global Management in a room to figure out the repairs. He has also said he is skeptical of some reasons given for the drawdown, and that whether the reservoir actually needs repairs remains an open question. FERC's directed drawdown, and the company's agreement to hold 1,200 feet until remediation is done, are already on the operating page.

Bethel can press. It cannot order the pond back up. Town Supervisor Daniel Sturm told The River Reporter the town has no legal jurisdiction over the reservoir, though it can apply political pressure.

Eagle Creek, Apollo Global Management, FERC and the Town of Bethel had not answered WAMC before publication. What is already in writing is the hold: at or below 1,200 feet until remediation is finished, with 2030 the earliest year neighbors have been given for testing and a hoped-for return of the water.