Boise's 8th Street Reopens After $2.8M Makeover, Some Amenities Still Missing

AI Assisted Icon
Published on November 19, 2026
Boise's 8th Street Reopens After $2.8M Makeover, Some Amenities Still MissingEureka! on 8th Street — Approximate Site of Affected Business
Google Street View

The fences are down and the full 8th Street corridor known as Boise's restaurant row is open to pedestrians again, capping off a $2.8 million makeover that stretched across months of construction, torn-up concrete and restricted walkways. Business owners along the corridor are hoping the new look brings people back, especially with the holidays approaching, even as crews still haven't finished installing everything that was promised.

According to BoiseDev, the project features dedicated pedestrian and bicycle zones along with new signage and accessibility improvements. Crews have not yet installed some promised amenities, including seating and overhead string lighting, the outlet reports. As reported by KTVB, the city plans to add movable tables and chairs, planters and benches next spring, along with overhead festoon lighting that has yet to go up.

City of Boise officials said phase two construction began near the beginning of May and was expected to wrap by the end of November 2026. Businesses were told they could stay open throughout, though existing patios would be temporarily reduced or removed during the work, the city said in its announcement. Planned improvements included bike parking, pedestrian walkways, signage, lighting, landscaping, public seating and accessibility upgrades.

Months of Narrow Sidewalks and Lost Business

For businesses along the corridor, the construction period meant restricted walkways and parking access that KTVB reports contributed to a significant drop in foot traffic. Sidewalks were narrowed to about four to five feet on each side, according to KTVB, squeezing pedestrian space on a street where large outdoor patios are usually part of the draw. Eureka! lost about a quarter of its weekly profits during construction, per the same report.

Brandon White, general manager of Eureka!, has watched 8th Street develop for more than a decade, according to KTVB. White said the street is designed for foot traffic and that its patios are what pull visitors in, and he hopes the completed project will bring people back, particularly around the holidays, when downtown foot traffic typically slows during colder months anyway.

At Dawson Taylor Coffee Roasters' downtown cafe, employee Amanda Stewart said the last two months of construction were noticeably quieter, the station reports. Stewart said the improvements have made the street more accessible for people with disabilities, even as the work disrupted day-to-day business.

Underground Problems Slowed the Timeline

The project ran into its own setbacks along the way. The contractor encountered unforeseen underground utility conflicts that required minor design modifications, and newly placed concrete that failed to meet project quality standards had to be dug up and redone, according to BoiseDev's September reporting. The contractor covered the cost of the redo and added crews to speed things up, BoiseDev later reported.

That earlier BoiseDev report, covering a separate $2.2 million phase of updates between Main Street and Bannock Street, found that a stretch of the block that was supposed to reopen September 4 remained barricaded while crews addressed the construction problems. The city had hoped to celebrate the project's full opening with an event October 1, per the outlet, and said the design changes would not cost the city extra.

Not every business owner along the corridor sees the finished product the same way. Andrew Echavarria told KTVB the changes were not very noticeable to him, though he said the pavement was even and restored. Ian Alvarado, meanwhile, questioned whether the improvements justified slowing downtown traffic and pedestrian movement in the first place.

A Street the City, Not the County, Controls

8th Street is unique in Boise in that it's controlled by the City of Boise rather than the Ada County Highway District, which oversees most roads and streets elsewhere in the county, according to BoiseDev. That distinction gave the city direct authority over the redesign, which also included underground utility upgrades, decorative colored concrete, new signs and bike racks, and a geothermal system intended to help heat downtown buildings, per KTVB.

Boise city planner Chad Rietze told KTVB the broader goal is to make 8th Street a place where people want to spend time, not merely walk through. The city has said it expects the north block to be fully open by Thanksgiving.

Whether the finished redesign will actually translate into more customers remains to be seen. A separate report on a 2020 car-free pilot on one block of 8th Street found businesses there saw a 29 percent boost in consumer activity compared with the rest of the city during that COVID-era period, according to KIVI-TV, and researchers at Portland State University found that pedestrian and cyclist traffic had a positive impact on sales, especially for restaurants, the station reported. That pilot program is a different undertaking from the current $2.8 million makeover, and no current data shows whether this project will produce a similar effect.