Interior Secretary Doug Burgum spent Nov. 11 at Fervo Energy's Cape Station near Milford and held the remote Beaver County project up as an example of the administration's energy-dominance agenda.
The plant he toured is no longer a rendering. Its first block is already in commercial service, most of the early contracts point to California, and a much larger Google agreement does not expect first power until mid-2028. KSL reporter Mike Anderson covered the visit.
A Cabinet Stop Near Milford
Burgum praised Cape Station as an example of President Trump's energy-dominance agenda. He described that agenda as energy abundance and as power that is reliable, affordable and secure, and he called geothermal a great reliable source. He also said Utah and the local community have supported the project.
Anderson reported that Burgum tied the stop to artificial intelligence as well. He said demand for AI-related capabilities would come from education, health care and end customers, and that expansion of AI infrastructure will play a key role in the nation's future. He said foreign influence has sought to persuade American communities and states not to build data centers. That was his account of the politics around server halls, offered at a geothermal field that does not yet have one.
KSL also reported that Burgum denied a ProPublica report's claim that he stands to benefit from an AI boom through his tech investments. He said the companies in question are small, privately held entrepreneurial startups, that none are building data centers or are hyperscalers, and that they were at risk of making very little profit. Those remarks were about the investments, not a forecast for Cape Station.
Thirty-Three Megawatts, On the Clock
Cape Station sits near Milford, in a part of Beaver County that already includes wind farms, solar farms and several geothermal projects. The new piece is enhanced geothermal on a commercial timetable. Fervo said Phase I GeoBlock 1, with 33 megawatts of capacity, declared commercial operation on Sept. 30. KSL's visit coverage put that output at about 33 megawatts for customers in California.
On X, @fervoenergy
called the startup commercial operations ahead of schedule and a first for greenfield enhanced geothermal, describing the product as 24/7, carbon-free, firm power. The calendar, at least, matches a promise the company made three years ago. In September 2023,
KSL
reported that Fervo expected Cape Station to begin delivering around-the-clock power to the grid in 2026 and to reach full-scale production in 2028. The first of those dates has arrived as a single block. Full scale has not.
Companywide, Fervo's third-quarter results put capacity in operation at 36 megawatts at the end of the quarter, up from 3 megawatts at the end of the second quarter, with 466 megawatts under construction. The 36-megawatt figure is Fervo's reported companywide operating capacity. The construction figure is the closer measure of what is actually being built.
California Buyers, Then Google
Most of Cape Station's early capacity is contracted under long-term agreements to California providers, including Southern California Edison, Clean Power Alliance and Desert Community Energy, KSL reported in October. Utah ranks third nationally in installed geothermal capacity and still accounts for only about 3.2 percent of the U.S. total. California and Nevada together hold more than 90 percent. A Beaver County project sending its first electrons west is less a plot twist than the existing map.
The Google contract is a different size. Fervo described a 15-year, grid-connected, take-or-pay agreement for 396 megawatts, with first power expected in mid-2028. Take-or-pay means the buyer is committed to the contracted volume, not shopping the plant's output week to week. Government Computer News called the deal the largest enhanced-geothermal power purchase agreement to date. Fervo had signed a 320-megawatt agreement with Southern California Edison in 2024.
Google's bet on the company predates Milford. Data Center Dynamics reported that the companies partnered on a Nevada pilot that came online in 2023, then signed a 115-megawatt agreement. KSL's visit story said Fervo plans to expand production to around 500 megawatts by 2028, close to the 466 megawatts already listed as under construction.
Other technology buyers are writing smaller checks for the same kind of firm power. Data Center Dynamics reported that Meta signed geothermal agreements for 150 megawatts each with Sage Geosystems and XGS Energy.
4.3 Gigawatts, Then 8.4
The long-range figure depends on the date and the definition, and the two are not interchangeable.
In October, KSL reported that Fervo predicted Cape Station could deliver 4.3 gigawatts at peak, with 3.4 gigawatts still unclaimed after the Google and California contracts. On Nov. 9, Fervo said an independent study supported approximately 8.4 gigawatts of capacity potential at the site, nearly double that earlier 4.3-gigawatt estimate. The company presented the later number as capacity potential. It did not say the two estimates used the same assumptions.
KSL's account of the Burgum visit used a third formulation: about 8 gigawatts if a data-center project proceeds. That condition is attached to a project that has not been built. It is not the same claim as the study's resource figure, and neither number is the 33 megawatts now in service or the roughly 500 megawatts planned for 2028.
A wider federal estimate sits even further out. A U.S. Geological Survey fact sheet on the Great Basin offers a provisional figure of 135 gigawatts of electric capacity from enhanced geothermal systems in the upper 6 kilometers of crust, if technological advances make that resource commercial. Cape Station is one company's attempt to move a slice of that geology onto a contract, not proof that the regional total is available to Beaver County.
A Data Center That Is Still a Maybe
Fervo said the Google framework could allow it to directly power a potential regional data center in Beaver County. KSL described the companies as in talks to supply power for a potential hyperscale data center near the site. As of a Sept. 2 report in The Salt Lake Tribune, the location of Google's potential data center was still unknown, and any plan was subject to market conditions, local permitting and engineering. A framework and a set of talks are not a permitted building on the Milford plain.
The electricity problem those talks are aimed at is already showing up in Utah. The Tribune reported that data-center developers have struggled to secure enough power from utilities and have turned to gas generators and self-contained plants. Fortune has described the AI boom's demand surge as one reason next-generation geothermal is now in the mix: buyers want power that runs when the sun is down and the wind is quiet.
Burgum's stop put a cabinet secretary next to the early version of that pitch. The operating block is 33 megawatts, online since Sept. 30 and contracted toward California. The 396-megawatt Google agreement is written for first power in mid-2028. Whether Beaver County also gets the data-center load that would use a later, much larger Cape Station is still a market and permitting decision, and it has not been made.