Westinghouse Electric Company has handed BWXT Canada purchase orders to build demonstration reactor components at two North American plants, a move that could position the Cambridge, Ontario manufacturer as a long-term supplier for nuclear projects around the world. The orders cover steam-generator demonstration pieces at BWXT's Cambridge facility and demonstration pieces of reactor-vessel internals at its York, Pennsylvania location, with the work tied to Westinghouse's AP1000 reactor design.
According to Business Wire, Westinghouse Electric Company and BWXT Canada have agreed that BWXT Canada will qualify to manufacture key AP1000 components to Westinghouse specifications. That arrangement gives BWXT Canada access to Westinghouse designs, manufacturing expertise, facilities and operational know-how, as reported by Investing.com. Once qualified, BWXT Canada is expected to function as a merchant supplier of these components for AP1000 projects worldwide, per the same report.
The qualification is not automatic. Business Wire's release notes that BWXT Canada has described the timing and outcome of qualification, its ability to meet manufacturing and quality requirements, project progression, and any additional commercial orders as uncertain, framing those statements as forward-looking. Investing.com likewise reports that the qualification remains subject to meeting manufacturing and quality requirements.
Why Canadian Manufacturing Capacity Matters Now
The stakes extend beyond one plant's order book. The AP1000 supply chain currently supports six operational reactors globally and 14 units under construction, the Business Wire release states, with Canadian firms positioned to support both those operating units and the ones still being built. Additional AP1000 units are reported to be under various contract phases worldwide beyond that count.
John Gorman, president of Westinghouse Canada, said Canada's nuclear industry has the expertise, workforce and manufacturing capabilities to support rising global demand for new nuclear energy. He added that combining BWXT Canada's capabilities with Westinghouse's AP1000 technology and global experience creates opportunities for Canadian industry to support nuclear projects both domestically and abroad.
John MacQuarrie, president of BWXT's commercial operations, said the agreement reflects global reactor vendors' confidence in manufacturing capabilities across Canada and the United States. He said BWXT is expanding its ability to manufacture large nuclear-grade components, develop specialized skills and build capacity for nuclear projects globally.
A Plant Already Busy With Nuclear Work
BWXT's Cambridge facility isn't starting from scratch. The plant underwent a CAD80 million (USD56 million) expansion launched in 2024 that added 55,000 square feet and increased the size of its commercial nuclear clean room by 40%, according to World Nuclear News. The same report notes BWXT was already building 48 new steam generators for the life extension and refurbishment of Ontario Power Generation's Pickering Nuclear Generating Station, and was separately fabricating the reactor pressure vessel for the Darlington SMR project.
Corporate-wide, BWX Technologies operates 19 manufacturing facilities globally and employs more than 11,000 people, per the same Investing.com account. The company has also built 14 strategic partnerships supporting U.S. and Canadian government work at more than two dozen additional locations, according to Business Wire.
How Canada's Deal Compares to Poland's Supply Chain Push
Canada isn't the only place Westinghouse is lining up suppliers for AP1000 builds. In Poland, IHI Corporation secured an engineering and early procurement order from Westinghouse for unit 1 of the country's first nuclear power plant, covering long-lead items for a reactor containment vessel and a steel module, according to Nuclear Engineering International. IHI aims to begin manufacturing its component sections at a Yokohama facility as early as 2028, with Poland's first plant targeting three AP1000 units coming online sequentially between 2036 and 2038, the outlet reported.
Heavy forging capacity remains a separate bottleneck across the industry. Westinghouse has identified a 15,000-ton press capable of taking 350-tonne ingots as its stated minimum for the largest AP1000 forgings, according to Environment+Energy Leader. That outlet notes Allegheny Technologies operates a 15,000-ton press meeting the nominal force requirement, but its roughly 175-tonne ingot capacity falls well below Westinghouse's 350-tonne minimum, and large-press scheduling for pressure-vessel sets has commonly run around four sets per year when competing with other orders.
Company Backgrounds
Westinghouse traces its roots to 1886 and says it pioneered nuclear power with the first commercial pressurized water reactor in 1957. The company is owned by Brookfield and Cameco, and according to Business Wire, its technology powers 56% of the world's nuclear power plants and fuels 41% of the world's nuclear fleet, with the company describing itself as maintaining nearly two-thirds of the world's nuclear fleet overall. BWXT, for its part, describes itself as a U.S.-based Fortune 1000 and Defense News Top 100 manufacturing and engineering innovator, and filed its annual report on Form 10-K for the year ended December 31, 2025. The company said it does not undertake to update forward-looking statements unless required by law.