CapMetro's board of directors was set to decide Monday whether to approve a contract worth more than $51 million to expand Plaza Saltillo Station and improve Red Line access in East Austin. The vote covers a package of upgrades at the station, located at the corner of East 5th Street and Comal Street, including double-tracking, a new platform and a string of pedestrian safety improvements along the corridor.
According to KXAN Austin, the proposed contract totals just over $51.1 million, made up of a $44.5 million base construction contract plus a 15% contingency. If the board signs off, the work would go to Jay-Reese Contractors, a firm that has previously worked on the Waterloo Greenway and the Longhorn Dam Wishbone Bridge projects in Austin, the station reports.
The expansion itself is a long list of fixes aimed at the stretch of track running through East Austin. Per the station's reporting, the plan includes double-tracking from Onion Street to Matamoros Street, two 280-foot side platforms, new signal improvements, and a bike and pedestrian path running from Chicon Street to Pedernales Street. Reconfigured and resurfaced sections of 5th Street are also part of the scope, along with pedestrian safety rail crossings planned for Navasota, Comal, Onion, Chalmers and Robert T. Martinez streets.
Why CapMetro Says the Upgrade Is Needed
CapMetro meeting documents cited by the station said the expansion is meant to improve commuter rail access for the growing area around the station. CapMetro's own project page, which describes the broader Red Line Improvements effort, says the agency and the City of Austin are working on upgrades along the corridor between Attayac Street and Matamoros Street, with plans to double track approximately one mile of the line and add a second platform to the station, along with additional crossings and positive train control modifications.
On the money side, the station's report says CapMetro has funding for the expansion available in its capital budget and anticipates additional funding support from the City of Austin. The station also reports that CapMetro received $18 million in federal funds through the U.S. Department of Transportation's RAISE grant program — the Rebuilding American Infrastructure with Sustainability and Equity program. That account differs from CapMetro's own project page, which describes an $18 million federal BUILD grant from the U.S. Department of Transportation awarded to the agency in 2023; the dossier does not resolve which grant program actually funded the project.
A Timeline That Has Shifted More Than Once
If the board approves the contract, construction is expected to begin in January 2027, with station platform and track infrastructure work starting in April 2027 and construction continuing into spring 2029, the station's report states. That schedule marks a change from earlier planning: a November 2024 project update from projectconnect.com had listed construction running from 2026 to 2028, while CapMetro's own project page said that as of early 2026, the project was still advancing through design with continued public input and that a construction timeline had not yet been determined.
The project's price tag has also grown over time. An October 2024 report from KUT described the double-tracking effort as a $32.2 million project, with the federal government covering more than half the cost, and that version of the plan called for roughly 0.7 miles of new track running from east of Robert T. Martinez Street to Onion Street. The proposed contract under consideration this week is just over $51.1 million, and CapMetro's project page describes closer to a mile of new double track. The dossier does not explain why the cost or the construction window shifted between those earlier accounts and the current proposal, and it does not establish how the board ultimately voted.