Sarasota County is weighing the future of the Blackburn Point Bridge, a one-lane swing span that has connected U.S. 41 to the north end of Casey Key in Osprey for 101 years. County officials say replacement may be necessary; residents and preservation advocates argue the historic bridge can be kept. No final recommendation or decision has been made.

According to Your Observer, the county is studying three options: do nothing, build a new swing-span bridge, or construct a bascule drawbridge. A plan for the bridge's future is tentatively scheduled to be presented to the Sarasota County Commission for discussion this month, the report said.

As first detailed in the Sun, the bridge is a single-lane concrete-and-steel structure less than 150 feet long, built in 1925, and listed on both the National Register of Historic Places and the Sarasota County Register of Historic Places. It has undergone about five alterations since construction, but its 2001 National Register nomination report found it had retained its physical integrity and character. The Sun notes that reports differ on the bridge's exact origin year, with some accounts citing 1926, and that the Sarasota County Commission reportedly prioritized building the bridge over a new administration building back in the 1920s, underscoring how long the span has mattered to the area's development.

Why The County Says Replacement Is On The Table

County officials have said preserving the existing bridge would be extremely costly and that repairs would overload detour bridges in the area, according to the Sun's reporting. The county also says the bridge fails minimum lane and shoulder-width standards, which limits its usefulness as an evacuation route, and that it falls short of pedestrian, bicycle and Coast Guard navigation standards. Officials cite structural, mechanical and electrical problems with the span as well.

Sarasota County spent $2.2 million on consultants in 2025 to develop three replacement designs, the Sun reports. County transportation staff and consultants have recommended replacement, citing the bridge's condition, repair challenges and safety concerns, according to MySuncoast. Published replacement estimates differ: the Sun reports a county estimate of $37 million to $57 million; SNN cited an estimate of $30 million to $50 million; and MySuncoast reported $65 million to $75 million, excluding potential approach-road widening. The figures have not been reconciled.

A Cheaper Fix, But With Caveats

Preservationist Tommye Whittaker has argued that refurbishment could cost less than one-fourth as much as a new bridge, according to the Sun. A preliminary review commissioned by the Sarasota Alliance for Historic Preservation put rehabilitation at about $6 million in 2028, with roughly $11 million in maintenance through at least 2043, MySuncoast reported. The review was preliminary, and Bach Steel had not conducted an on-site evaluation.

A separate estimate reported by Bay News 9 put renovation costs at $31 million, with officials predicting the bridge would have only about 10 years of service left even after repairs. The Alliance has argued that keeping the existing steel structure could carry a lower environmental and carbon footprint than demolishing it and building new, per MySuncoast.

Petitions And Pushback From Residents

Opposition has taken the form of petitions and a proposed alternative. Whittaker started a petition opposing demolition with a goal of 50 signatures; by Friday it had more than 275, the Sun reports. Your Observer reported that the Sarasota Alliance for Historic Preservation had gathered nearly 2,000 signatures on a Change.org petition, as well as handwritten signatures at community meetings. The Alliance opposes demolishing the operating bridge and proposes modifying it to add a pedestrian and bicycle lane while retaining vehicle access.

Alliance members, including Randy Kowalski and Venice historian Larry Humes, have argued that retaining the bridge would preserve local history and Casey Key's character. Humes has questioned the need for a four-lane bridge, noting that the key's northern tip has about 250 residences and limited room to expand. Kowalski has described replacement as solving a “non-problem,” arguing that the southern bridge already handles traffic and emergency vehicles.

Kowalski has also argued that a larger replacement could change the character of the area, while the Alliance has warned that wider designs could encourage faster driving, according to the Sun. Residents' objections center on whether the safety and access concerns cited by the county justify replacing the historic span.

What The County Says Is Still Undecided

The Sarasota County public information department has said the county has not decided whether to repair and retain the bridge or replace it, according to the Sun's reporting. The Sarasota County Historic Preservation Board must review the historic site before the county can act on either option. County spokesperson Sara Nealeigh said in an email cited by the Sun that the county will acknowledge the historic bridge's significance if a replacement is ultimately chosen, though details of what that acknowledgment would look like are still being worked out. Nealeigh also said no commission vote on the bridge has been scheduled.

A Sarasota County notice describes a formal public hearing as tentatively scheduled for fall 2026, though the county characterizes that date as tentative rather than confirmed. Separately, a project page maintained by MyCaseyKey states that construction funding has not yet been identified in the county's current Capital Improvement Program, and that a formal public hearing before the commission is expected once the planning study is complete.

What Must Happen Before a Decision

The county said its Project Development and Environment (PD&E) study will assess effects on air and water quality, wildlife, wetlands and nearby communities, along with costs and potential economic benefits, according to Sarasota County. The county's notice, linked above, describes the formal public hearing as tentative for fall 2026 and says the study will proceed afterward under direction from the County Commission. The Historic Preservation Board review described above is also required before the county can act.

A Precedent From The Florida Keys

Supporters of preservation have pointed to the Old Seven Mile Bridge in the Florida Keys as a model for what's possible. That 110-year-old, National Register-listed span was converted into a pedestrian and bicycle walkway in 2022 following a $44 million restoration, according to reporting from News 13, with rehabilitation construction having begun in late 2017. The Alliance has cited that project in arguing for a similar approach at Blackburn Point — retrofitting the existing bridge with a pedestrian and bicycle lane rather than tearing it down.

For now, the fate of the Blackburn Point Bridge remains unresolved. County officials maintain no decision has been made and no commission vote has been scheduled, even as residents keep adding signatures to petitions and pressing for a seat at the table before any final call is made.