An 11-story condominium on West 19th Street has topped out and lost the black netting on its southern face, but the finish has slipped from last summer into next year.
In a report published Saturday, New York YIMBY said 227 West 19th Street, between Seventh and Eighth Avenues in Chelsea, is now projected for completion in 2027. The same account had previously listed August 2026, a date noted on site.
Eight Homes, Not a Full Floor Plate
DXA Studio designed the building for a joint venture of RoundSquare Development and VM Properties Group. At 100 feet and 37,378 square feet, it is a narrow Chelsea infill job rather than a tower.
The plan yields eight condominiums: five full-floor three-bedroom homes, two four-bedroom penthouses, and a four-bedroom townhouse with a private garage. Residences are described as 35 feet wide, with outdoor space built into the apartments rather than treated as an afterthought.
Shared amenities include a fitness center, concierge service, and a rooftop terrace. For a building this small, the garage and the roof may do more marketing work than the gym.
Brick, Bays, and an L-Shaped Top
The massing stays uniform through the eighth floor. Loggias frame a setback on the eastern half, and the last three stories step into an L. A flat roof carries a light gray rear bulkhead.
The façade is red brick, with fluted bond patterns on the angled walls behind the balconies and across the first two stories. Scaffolding and black netting that had covered the southern elevation were recently removed, exposing angled bay windows and pleated balconies. YIMBY also reported that the building has been enclosed in that brick skin.
From Halfway Up to a Later Finish
The construction clock is easier to follow than the sales one. In July 2025, New York YIMBY reported that the reinforced-concrete superstructure had passed the halfway mark and could likely top out before the end of that summer. That update still carried an August 2026 completion date.
By the November 2026 report, the building had topped out since that July update, with completion projected for 2027. No finer completion date is in the latest account.
What the Sponsors Paid to Get Here
The site changed hands before the concrete did. CityRealty reported that the RoundSquare and VM Properties joint venture bought 227 West 19th Street from JT Falk & Co. for $5.95 million in October 2023.
ConnectCRE reported that Urban Standard Capital provided a $13.8 million acquisition and construction loan for the Chelsea condominium project. Michael Horowitz of Cooper Horowitz brokered the financing. The loan is for acquisition and construction, not a statement of total project cost or of what the eight homes will sell for.
A Short Walk to the 1
YIMBY identifies the closest subway as the 1 train at 18th Street station on Seventh Avenue, near the site. That is the practical neighborhood fact attached to a building that is still a construction project, not a finished address.
The southern elevation is now readable from the street, the frame is done, and the posted target has moved from August 2026 to sometime in 2027.