Greater Providence/ Parks & Nature

Collierville, Tennessee, Approves W.C. Johnson Park Boardwalk Renovation

AI Assisted Icon
Published on November 18, 2026
Collierville, Tennessee, Approves W.C. Johnson Park Boardwalk RenovationW. C. Johnson Park Dr. — Local Street Scene
Google Street View

The oldest run of boardwalk at W.C. Johnson Park in Collierville, Tennessee, is slated for renovation. The town approved work on roughly 1,000 linear feet, the line from the Nature Center to the overlook gazebo.

The Town of Collierville posted an update about the improved boardwalk in a Facebook post.

The Stretch Built in 2000

Those thousand feet were the original section, not a random patch of tired lumber. An August 13, 2026, account on laurenhaynesrealtor.com described a 1,000-linear-foot segment built in 2000, running from the trailhead at the Nature Center to the overlook gazebo. That is the same span targeted for renovation.

Getting to it meant shutting more than the work zone. Collierville closed the entire boardwalk on June 15, 2026, to rebuild that oldest stretch. Newer sections went offline with it.

By the time crews started pulling boards, the original run had been in place for 26 years.

Five Bids and a 110-Day Clock

On May 11, the Board of Mayor and Aldermen approved a construction-services contract to renovate the original 2000 section, Citizen Portal reported. Five bids came in. Nabholz Construction was the lowest apparent bidder.

Nabholz was awarded the contract for $429,512.46, against a $454,000 project allocation. Citizen Portal also reported that the project budget required an $8,678 draw from CIP contingency.

The contract allowed 110 days of work and set a projected completion deadline of October 3, 2026.

What the May Plans Described

The renovation approved that spring was drawn as more than a deck swap. Citizen Portal described a concrete approach with an ADA-accessible ramp leading to a boardwalk raised roughly 20 inches, and reconstruction of the gazebo on helical piers.

Back from the Nature Center

The replaced run is a specific walk, not the whole park inventory. It starts at the Nature Center trailhead and ends at the overlook gazebo, the 2000 section targeted for renovation.