Columbus could be asked to write a power limit for data centers into the city charter. Conserve Ohio has been cleared to gather signatures for an amendment that would prohibit construction of data centers using more than 25 megawatts.
The campaign needs 12,500 signatures and wants the measure ready for the November 2027 election, NBC4 reported. That is a long path, and it starts after a November in which other Ohio communities already rewrote their rules, and after City Council spent September on utility charges rather than a pause.
What the 25-Megawatt Line Does
Conserve Ohio filed a petition for a charter amendment restricting data centers above that 25-megawatt threshold. Nick Owens, with the group, said the line is meant to allow a data center needed for ordinary day-to-day use while aiming at larger facilities.
The number is doing a lot of definitional work. Twenty-five megawatts is also five times the electrical cap Cuyahoga Falls just set for the smaller facilities it will still allow. As NBC4 described the Columbus proposal, the prohibition is aimed at construction of centers that use more than 25 megawatts, not at every room with a server rack.
Kim Kinder-Smith told NBC4 that Columbus had no data center projects in process or requested. On that account, the amendment would bind construction that has not yet been asked for inside the city, rather than stop a project already moving through City Hall.
Fees Instead of a Moratorium
In September, Columbus City Council was considering regulations aimed at data centers' effects on utility costs and pollution, and it was not pursuing a temporary moratorium, WOSU Public Media reported.
The ideas on the table included a new set of rates, charges, or fees for high-load, high-volume water users; decommissioning rules; water conservation plans; and measures addressing environmental effects of on-site power generation. A proposed rate package had received a first reading and, at the time, could have come up for a final vote at the next meeting.
Council member Christopher Wyche said data centers were not being built within city limits and called a moratorium performative. Council President Shannon Hardin is co-sponsoring legislation with Wyche that would charge data centers for peak water usage, The Columbus Dispatch reported.
The water bill is where the city boundary gets porous. Most of the region's largest data centers are outside Columbus, the Dispatch reported, but many get water from Columbus Water & Power. A charter rule on construction inside the city would not, by itself, price the campuses already drawing on that system.
The Economic Case and the Poll
The Ohio Chamber of Commerce says data centers have contributed more than $9 billion to Ohio's economy. Dorsey Hager told the Dispatch that three Google campuses, in Columbus, Lancaster, and New Albany, provided the building trades 6.5 million work hours last year.
A survey WOSU cited points the other way. A Bowling Green State University poll of 1,000 likely voters found that 78% strongly favored or favored a temporary ban on new data centers until more information was available about their effects. In the same poll, 75% opposed a data center being built in their own community.
How Other Ohio Rules Landed
Ohio had more data center-related ballot measures than any other state, and measures to limit the developments passed with a large margin of support statewide, the Statehouse News Bureau reported on Nov. 10. The bureau also reported more than 200 data center projects planned or under construction in Ohio, the fifth-highest number in the nation.
Published tallies of what passed should not be stacked into one total. NBC4 reported that ten Ohio communities voted to ban hyperscale data centers, and, in its account of the Columbus petition, that three central Ohio communities passed data center bans during the midterms. Cleveland.com reported that voters in 11 municipalities approved charter amendments aimed at restricting large-scale data centers. Those descriptions are not the same claim.
Grove City's amendment was a vote requirement, not a flat prohibition. Voters approved a charter change requiring a citywide vote for certain developments that meet size, power-use, or water-use thresholds. It passed with 54.6% of the vote.
Trenton went further on paper. Voters passed a November charter measure that Local 12 described as practically banning large-scale data centers. Prologis is suing the city, arguing the amendment cannot lawfully apply to its project because that project was approved before the vote.
Cuyahoga Falls used council legislation. Large-scale data centers are prohibited, while manufacturing and industrial businesses may house smaller data facilities. Individual buildings may not exceed 5,000 square feet, no more than one is permitted on a property, electrical demand is capped at five megawatts, and water consumption is subject to approval.
Signatures, Then November 2027
Before any of that becomes a Columbus ballot question, the paperwork has to hold. The city clerk sent the petition's pre-circulation copy to the city attorney and requested a written legal opinion on whether it addressed a single subject and met form requirements, NBC4 reported. The campaign has since been cleared to start gathering signatures.
A city presentation on initiated petitions says a committee has one year to gather signatures before turning completed part-petitions in to the City Clerk. Conserve Ohio's stated target is still 12,500 names and a November 2027 election.