Paddlers hoping to use Conneaut Township Park's new creek drop-in point will have to wait a little longer, even though most of the construction work is already finished. The Twin Bridges Water Trail project has been completed aside from a couple of little things remaining, and officials say the trail will be fully operational next year.
The project, reported complete according to an Eastgate Regional Council of Governments press release cited by the Star Beacon, created a creek drop-in point at the former Farnham Park on Center Road and improved a paddler exit point on Old Main Road, both in Conneaut. Conneaut Township Park has owned the Farnham Park property since 1946, according to Michael Smith. The two locations sit a couple of miles apart by road, Smith said, but more than five miles apart along the water itself.
What Got Built at Each Site
The Farnham drop-in site now includes a paved, gated walkway leading to a new concrete pad at the water's edge, along with paved parking spaces running along Center Road, per the same report. Over on Old Main Road, crews paved and striped what had been an existing dirt parking lot, giving paddlers a formal spot to pull in and out. Both sites are set to get large signs identifying the trail's drop-in and take-out points next year.
Grant funding also allowed for an unexpected addition at the Farnham site: a floating dock system attached to a gangway hooked to shore. Conneaut Township Park personnel installed the dock in the water at the end of October for an installation deadline, then pulled it back out about a week later ahead of winter. The system, dubbed EZ Dock, is expected to be reinstalled next spring once weather permits, with the floating dock set to greet paddlers in early 2027.
A Delayed Timeline
A Delayed Timeline The Twin Bridges project was originally scheduled for completion by midsummer 2026, but Geauga Highway of Middlefield was the contractor and construction was pushed back. That's a shift from earlier expectations: the Star Beacon reported in 2026 that foul weather had delayed construction and that the access point was expected to welcome its first paddlers in July, while the Meadville Tribune had earlier reported that additional access to Conneaut Creek was expected before the end of summer. Those were forecasts rather than confirmation that the trail was open, and the project ultimately wrapped up later than planned.
Despite the delay, Smith said Conneaut Township Park commissioners are very pleased with the result, especially because the work required no local matching money. The commissioners received funding through Ohio's Appalachian Community Grant Program, though the reported dollar figures vary depending on the source: the Star Beacon's current account cites $276,187, an earlier Star Beacon article on the project cited a $276,000 award, a state grant-list document from the Ohio Governor's office lists an Appalachian Community Grant award of $276,187 for the Twin Bridges Kayak Launch and Water Trail project, and the Gazette News reported an award of approximately $187,000. It is not clear from available reporting whether these figures describe the same award, different phases of funding, or separate scopes of work.
Officials Tout Expanded Access
Eastgate Regional Council of Governments, which handled project finances on behalf of Conneaut Township Park, called the water trail a boon for the area. Kevin Lemmo praised the project in a statement, saying the launch is a fantastic addition to Conneaut Township Park and that the Twin Bridges Water Trail opens Conneaut Creek to more families and outdoor enthusiasts.
Kathy Zook, Eastgate's Appalachian Regional Commission program manager, said waterways are incredible regional assets and that improved waterway access is essential for local recreation. She added that the new launch strengthens the Twin Bridges Water Trail network and ensures paddlers have safe, reliable access to enjoy the creek.
The grant funding supported improvements at both locations, and the two kayak launch points were originally pitched as a way to create the Twin Bridges Water Trail between the creek's twin bridges, according to a project description included in Ohio's Appalachian Community Grant Program funded-projects document. An earlier Meadville Tribune report noted that Geauga Highway had been hired to build the Farnham access point. For paddlers planning ahead, American Whitewater describes the relevant stretch of Conneaut Creek as a 9.7-mile river trip requiring roughly a 3.5-mile shuttle, and notes that water levels below about 2.0 feet, or roughly 175 cubic feet per second, can turn a float into more of a walk.