A drought that dried up private wells across the Orland area several years ago set off a $16.7 million effort to shore up the city’s water system, and the city now plans to mark the project’s final major piece with a ribbon-cutting ceremony scheduled for noon on Monday, November 23, 2026. The centerpiece is a one-million-gallon water storage tank built to secure supply for properties that lost access to groundwater during the dry years.
The project traces back to the severe drought that gripped the region from 2020 through 2022, when private wells throughout the Orland area began running dry, according to Action News Now. The City of Orland responded by undertaking a broader water-system improvement effort, and in September 2021 it began working with the California Department of Water Resources on upgrades meant to address the shortage, per a City of Orland meeting packet.
What the Project Is Meant to Fix
City officials have described the primary goal as supplying residents both inside and outside city limits with a safe and reliable source of drinking water, the meeting packet states. DWR ultimately provided $16.7 million in total funding for the effort.
The new tank is designed to secure water supply for local properties affected by the dry wells and is considered the final major component of the broader Orland Area Water Supply Project, which aims to improve long-term water reliability. City officials have said the infrastructure is meant to strengthen water security for residents for years to come, and Orland has expressed gratitude to the state water agency for its partnership and funding support, according to the seed report.
Construction Phases and Timeline Shifts
The project has unfolded in phases. Phase 4, which includes the one-million-gallon tank along with booster pumps and related site improvements, represents the work now nearing completion. An earlier stage, Phase 2A, included roughly 5.1 miles of new water main and 97 water service connections, the meeting packet notes.
Completion estimates have shifted over time. As of mid-September, construction stood at 65% complete and was expected to wrap by summer 2026, according to the Chico Enterprise-Record. By December, a city meeting packet put progress at about 75% complete and projected the tank would come online in July or August 2026.
How Many Households Benefit Remains Unsettled
Reports have differed on exactly how many households the project serves. One account from KRCR said Orland anticipated connecting 168 households, including about 34 inside city limits with the remainder in the surrounding county. A separate 2022 report from the Enterprise-Record said DWR had identified around 150 homes to qualify for connection. The dossier does not resolve whether these figures reflect different project phases or simply differing counts at different points in time.
The project’s budget has also been described somewhat differently across years of coverage. A 2022 Enterprise-Record report put the construction and design budget at more than $16.7 million, while the December 2025 city meeting packet describes $16.7 million as the total funding DWR provided for the project. It is not clear from available records whether these reflect the same figure described differently or a change in total project cost over time.
A Earlier, Related Pipe Program
The tank project follows an earlier push to extend pipes to residents just outside city limits. In 2022, Orland laid out plans to build water pipes connecting dry-well owners in the county, with lateral lines, meters and house connections offered at no charge to participating residents, Action News Now reported at the time. That earlier program drew interest from 237 people and was expected to cost nearly $12 million.
With the tank nearing its final stretch, the planned ribbon-cutting is meant to mark the culmination of years of work that began with residents watching their wells run dry. The ceremony is set for Orland, California, bringing a years-long infrastructure push closer to the reliability city officials say they set out to deliver.