After five years of fences, detours, and delayed timelines, the East River Esplanade along the Upper East Side has largely reopened to walkers, runners, and cyclists, restoring a continuous waterfront route of about 3.5 miles. The East 72nd-to-78th Street section reopened Wednesday, November 18, after more than four years of construction.
Upper East Site reported Thursday that the Esplanade had fully reopened after years of construction and repeated delays. That account lines up with Patch, which reported the reopened path now connects more than 60 contiguous blocks of public waterfront access spanning roughly 3.5 miles, with the section between East 72nd and East 78th Streets reopening after several years of construction. The work, per Patch, included strengthening the seawall, adding a crash-rated barrier along the FDR Drive, and repairing sinkholes, along with new pavers, landscaping, an irrigation system, outdoor fitness equipment, and security cameras.
The Hospital for Special Surgery has been rebuilding its stretch of the Esplanade while constructing its Kellen Tower above the FDR Drive. The East 72nd-to-78th Street section reopened on November 18, 2026.
A Timeline Stretched by Sinkholes and Snags
Our Town had reported a later target for the section. The outlet quoted Parks Department Chief of Staff Steve Simon saying officials then anticipated completing topside improvements the week of November 23, at which point the section between 72nd and 78th Streets would open to the public. Our Town also reported that sinkhole-related work had forced the closure of two Esplanade entrances, one at East 78th Street and one at East 81st Street, further complicating access to the corridor.
The closures trace back to 2022, when a nine-block section of the Esplanade starting at East 70th Street first shut down, according to Our Town. A June 2025 Community Board 8 meeting record shows the scope and sequencing of that work: improvement efforts between East 72nd and East 78th Streets were slated to begin in August 2025 and unfold in four phases, with Phase 1, covering East 70th to East 73rd Streets, scheduled to run from August 2025 through January 2026. A separate Patch report from that period said the East 72nd-to-78th Street stretch had been set to reopen October 31, but that date was delayed.
Progress Has Come in Pieces
Some parts of the project have already crossed the finish line. HSS says the East 70th–71st Street section is fully open, with a new permanent pedestrian ramp at 71st Street that opened in June 2026. East Side Feed reported that the East 70th-to-71st Street stretch, including the pedestrian bridge and ramp, reopened on June 15 after Parks crews fixed two sinkholes in that area. The East 78th Street pedestrian bridge is also open again, HSS says, following a temporary closure earlier in the summer.
Although the East 72nd-to-78th Street section has reopened, the broader Esplanade won't be entirely finished. Patch reports that renovations to the rest of the corridor, overseen by the Parks Department and the New York City Economic Development Corporation, are still underway. For Upper East Siders who have navigated detours around this stretch of waterfront for half a decade, the project has missed deadlines before.