Eliot Arts Magnet Tower's Fate Still Unresolved Nearly Two Years After Eaton Fire

AI Assisted Icon
Published on November 19, 2026
Eliot Arts Magnet Tower's Fate Still Unresolved Nearly Two Years After Eaton FireSource: Google Street View

Nearly two years after the Eaton Fire forced Eliot Arts Magnet Academy's students out of their Altadena campus, Pasadena Unified School District still has not decided what to do with the school's landmark tower — or when students might finally get to go home. Preliminary district estimates now put occupancy at roughly 53 months for a brand-new replacement campus, or about 71 months if the original tower is kept standing, an 18-month gap that could shape how long Eliot's community stays displaced.

The district is weighing three options: keeping the original tower, preserving select historic architectural features, or constructing an entirely new campus designed to echo Eliot's historic character, according to Pasadena Now. Neither the tower's ultimate future nor a reopening date for the school has been established, the outlet reports. Eliot students and staff were relocated after the January 2025 wildfire tore through the area, and they have since been attending classes at McKinley School in Pasadena, according to the Los Angeles Times, which described rebuilding the school known for its imposing bell tower as a years-long project.

A Reversal Over the Tower's Safety

The uncertainty traces back to a whiplash moment earlier this year. On May 6, the district said structural assessments had turned up significant fire-, heat- and seismic-related concerns, and that the remaining structures — including the tower — were unsafe, per the Pasadena Star-News, which quoted the district saying “significant structural concerns were identified, including fire, heat and seismic-related impacts.” Less than two weeks later, Superintendent Elizabeth Blanco reversed course, announcing the district would instead conduct a yearlong environmental impact report to determine whether the tower could remain or would need to come down.

“The Pasadena Unified School District will conduct a yearlong environmental impact report on the beloved tower at Eliot Arts Magnet Academy to determine whether the structure is safe to remain or will need to be demolished,” Blanco said, according to the San Gabriel Valley Tribune. At the time, Michael Dunning said the environmental review could take up to a year on top of the three years already estimated to rebuild Eliot — an earlier timeline that differs from the district's more recent estimates of 53 to 71 months. Blanco also said the district may explore building a replica of the tower if engineers determine the original cannot safely remain.

Engineers Still Studying the Structure

Engineers are now conducting additional structural evaluations to determine whether the tower can be retained and what seismic safety upgrades it might require, per the same account from Pasadena Now. The district reviewed a historic resources evaluation in September, and it says it is advancing environmental consulting, architectural coordination, structural investigations and educational master planning simultaneously where possible, in hopes of trimming delays.

The outlet reports that the district's October planning update identified Nov. 1, 2027, as a milestone for reviewing design alternatives, estimated costs and projected construction schedules — not a reopening date or a final-design decision. The district says it will update its preliminary timeline estimates as engineering studies and campus planning move forward, and it also estimates the environmental impact report process could take roughly 12 months once fully underway.

Two Rounds of Public Comment Ahead

Residents will get two formal chances to weigh in under the California Environmental Quality Act, the district says. The first comment period begins once the district issues a notice of preparation and will run 30 days, covering public input on what the environmental impact report should examine. A second period, lasting generally at least 45 days, will follow publication of the draft report — though dates for either window remain unannounced.

Once environmental review wraps up, the district plans to evaluate public comments, prepare a final environmental report, and bring proposed project directions before the Board of Education for consideration. That board had already signaled its intent to save what it could of Eliot's character: on Jan. 30, 2025, it adopted Resolution No. 2800, affirming a commitment to rebuilding the school while honoring its distinctive architecture, after dozens of community members spoke in support at the meeting, according to the Pasadena Star-News.

A Slow Rebuild Across a Scarred Neighborhood

Eliot's halting timeline mirrors a broader, sluggish recovery across Altadena. The Eaton Fire destroyed 6,746 homes in the area, and about a third of burn sites were still under construction as of a recent report from The Architect's Newspaper. A June 2025 survey by the Greenline Housing Foundation found homeowners trying to rebuild faced an average funding gap of $268,000, underscoring just how much financial and logistical friction stands between fire-affected families and anything resembling normal.

For now, Eliot's roughly 53-to-71-month occupancy window leaves the arts magnet's community facing years more at McKinley School before any decision — tower intact, partially preserved, or rebuilt from scratch — becomes reality.