A vacant stretch of land near Dallas Love Field Airport could soon become the site of a $500 million data center, after an Equinix affiliate filed plans for a four-story, 372,445-square-foot facility at 1520 West Mockingbird Lane. The filing, submitted to the Texas Department for Licensing and Regulation, lists construction running from February 2027 to December 2029, though the project remains in the planning stage rather than under construction.
The filing, first reported by Data Center Dynamics, identifies the project as DA13-1, located in Dallas County. The site sits in an industrial area near the airport and is currently vacant. It was previously occupied by Mockingbird Office Park, which stood there from the 1970s until it was demolished around 2022, according to the outlet's reporting.
The property has changed hands more than once in the past decade. The site, formerly known as Oakbrook Plaza, was acquired by 2GR Equity and Legacy Capital in 2016, then picked up by Center Court Partners in 2019, per the same report. The entity behind the new filing, DA12 LLC, shares a listed address with Equinix, and Arquelle Shaw — identified as Equinix's Americas president — is listed as the LLC's contact.
A Second Mockingbird Lane Project Already Underway
DA13-1 isn't the only Equinix project taking shape along the same corridor. The company filed to develop two other buildings, DA12-1 and DA12-2, directly across the street at 1550 West Mockingbird Lane in November 2025, the report notes.
Those two filings carry their own price tags and timelines. DA12-1 is planned as a four-story facility with a $542.8 million investment and construction scheduled from February 2026 to October 2027, according to the article. DA12-2 is planned as a separate four-story building with a $293.7 million investment, with construction set for September 2027 to March 2028.
Reports differ slightly on the exact footprint of DA12-1. Data Center Dynamics cites a planned area of 372,515 square feet, while the Dallas Morning News puts the figure at 372,517 square feet. Either way, the two numbers are close enough to suggest both outlets are describing the same building.
What Stood There Before
The DA12-2 site has its own layered history. It was previously occupied by Taylor Publishing Company and, later, Balfour Publishing, with the existing building demolished ahead of the planned development. The Dallas Morning News adds that Equinix has owned the Mockingbird Lane property since June 2024, and that a separate DA12 filing covers interior fit-out work for the first and second floors, with estimated construction costs of nearly $294 million.
Taken together, the three filings point to a company moving aggressively to expand its Dallas-area footprint. Equinix already lists eight data centers around the Dallas area and one facility in Houston, a presence that would grow further if all three proposed Mockingbird Lane buildings move forward as filed.