Greater Tucson/ Tucson/ Transportation & Infrastructure

Grant Road Underpass Reopens With Six Lanes After Three-Month Tucson Overhaul

AI Assisted Icon
Published on November 21, 2026
Grant Road Underpass Reopens With Six Lanes After Three-Month Tucson OverhaulGrant Rd. & I-10 Frontage Rd. — Approximate Reopened Six-Lane Underpass
Google Street View

Tucson officials gathered Friday morning to cut the ribbon on the newly widened Grant Road underpass at the Union Pacific Railroad, marking the end of a three-month construction push that expanded the crossing to six total lanes. The ceremony drew city officials, members of the Pascua Yaqui Tribe, representatives from the Arts Foundation for Southern Arizona, and Regional Transportation Authority representatives, according to AZPM.

The project broke ground on May 22 with KE&G Construction working under contract with the city's transportation department, and the stretch between the I-10 westbound frontage road and Flowing Wells Road reopened to traffic at 4 a.m. on August 1, according to KVOA. Even after cars started rolling through again, KE&G crews stayed on-site through the end of August to wrap up remaining tasks, the station reported. An earlier estimate from city transportation officials, cited by the Tucson Sentinel, had pointed to September as the finish line for the entire project.

What Changed Beneath the Tracks

The finished underpass now includes a left-turn lane for I-10, updated traffic signals, new crosswalks, extended sidewalks, and improved street lighting, per AZPM's reporting. KVOA's earlier coverage similarly described enhanced ADA access and stormwater drainage improvements as part of the same scope of work. Before the overhaul began, KGUN 9 reported that eastbound drivers trying to reach westbound I-10 were down to a single left-turn lane during construction, a squeeze that's now been resolved with the added lane.

Ward 3 Councilmember Kevin Dahl attended Friday's ceremony and said, per AZPM, that Grant Road needed another lane because of traffic congestion near the newly opened Casino Del Sol. The project traces back to a Regional Transportation Authority plan approved by voters in 2006, which was designed to improve safety and mobility in and around downtown Tucson, according to the same report.

Detours, Timing, and What's Still Ahead

Before the closure, suggested detours routed drivers through Miracle Mile, Speedway Boulevard, and the I-10 frontage roads, KGUN 9 reported. The city intentionally scheduled the work for summer, when traffic is typically lighter as seasonal residents leave Southern Arizona, a city transportation spokesperson told the outlet at the time.

City officials said additional improvements are still planned for the area, according to AZPM. Among them is a mural by artist Joe Pagac, expected to be completed in the area in December — a detail that lines up with KVOA's earlier report that a mural was planned for the space east of the existing railroad bridge that same month.