Isle of Palms Finishes $7M Flood Barrier Phase, Five Homes Await Phase Three

AI Assisted Icon
Published on November 19, 2026
Isle of Palms Finishes $7M Flood Barrier Phase, Five Homes Await Phase ThreeLowcountry Skyline Viewpoint — Scenic Weather Coverage Backdrop
Google Street View

Isle of Palms has finished Phase Two of its long-running Waterway Boulevard flood barrier project, raising the pathway between 21st and 41st avenues to an elevation of 7 feet and installing drainage upgrades meant to keep tidal water out of island streets. City leaders are set to celebrate the milestone with a ribbon cutting at 10 a.m. Wednesday, Nov. 25, marking another step in a project that has ballooned from a simple sidewalk fix into a multimillion-dollar flood fight.

The completion was first reported by Live 5 News, which noted the project now costs roughly $7 million and is funded through a mix of federal, state and city money. The outlet reported that the effort traces back to a 2023 nor'easter that flooded numerous Isle of Palms neighborhoods and pushed city leaders to act on chronic tidal flooding along Waterway Boulevard.

Raising the Road, Blocking the Tide

Phase Two's work between 21st and 41st avenues included raising the path itself and adding localized drainage systems, according to Island Vibes. The outlet reported that crews installed in-line check valves on every outfall pipe discharging into the Intracoastal Waterway, a measure designed to stop tidal water from backing up into the drainage system during high tides. Isle of Palms Mayor Phillip Pounds said the work included both path and drainage improvements, adding, “There is a significant amount of drainage infrastructure on the golf course and along the road that we put in as a result of this project.”

Despite the new hardware, the project's own manager cautioned that the tidal protections remain unproven against a real test. Per the same outlet's report, the manager said the tidal protection components have not yet been tested by a major coastal storm or severe tidal event — meaning islanders won't know how well the system performs until the next big blow.

From Golf Course Berms to a Decade-Long Build

Phase Two builds on earlier work at Harbor Golf Course, where crews built new berms to hold back rising water as part of Phase One. Phases 1 and 1a wrapped in fall 2025 and included a $1.5 million flood barrier at the golf course along with elevation work on holes 9 and 10, Island Vibes reported. Council member Scott Pierce has said the overall Waterway Boulevard sidewalk and flood mitigation effort, spanning 21st to 41st Avenue, has been in progress for roughly ten years — a timeline Live 5 News detailed in earlier coverage of the project's ballooning budget, which started at just over $1.1 million before climbing to its current $7 million price tag.

What began as a basic sidewalk repair effort has since evolved into a multi-phase flood mitigation project, the station reported, reflecting how quickly the scope grew once tidal flooding became the priority rather than simple pathway repairs.

Phase Three Still Needs Easements From Five Homeowners

Attention now turns to Phase Three, which covers two gaps near 3607–31615 Waterway Boulevard that remain in the design phase. A city committee voted on Nov. 4 to approve a study and topographic survey for that segment, which affects five homes in the 3600 block, according to citizenportal.ai. The contract for that work came in just under $42,000 and is meant to prepare easement plats and concept materials ahead of formal design and construction.

City staff told the committee that the five affected property owners have verbally agreed to participate, but formal easements still must be secured before final design can move forward, the same outlet reported. Staff said the survey is a prerequisite for easement acquisition and further design work, and that they plan to return to the committee with finalized plats and next steps once that groundwork is complete. Phase Three is expected to start in early 2027.

A Second Trouble Spot Near the Marina

A separate stretch of the project, near the Deweese Island marina, has stalled because the marina's owner has not cooperated with the city, per citizenportal.ai's reporting. Staff are now re-evaluating placement of that flood protection in the public right-of-way near Fire Station Two instead. One option under consideration is elevating 41st Avenue itself, though the outlet reported that option may require its own separate design and a South Carolina Department of Transportation encroachment permit.

Earlier reporting on the broader corridor noted that paving for the Waterway Boulevard path and roadway was declared complete, with roughly a month of cleanup and landscaping work remaining at that stage, according to citizenportal.ai. The same report noted that several driveways still needed grade adjustments so water would flow properly into the new drainage system — a detail of the kind of granular fixes still trailing a project that has grown far beyond its original scope.