Jacksonville/ Transportation & Infrastructure

Jacksonville I-10 Nears 10 Lanes Between I-95 and I-295

AI Assisted Icon
Published on November 17, 2026
Jacksonville I-10 Nears 10 Lanes Between I-95 and I-295I-10 & I-95 — Approximate I-10 Widening Corridor
Google Street View

Interstate 10 between I-95 and I-295 is supposed to come out of its rebuild as a 10-lane road, five each way. Traffic has been shifted into the final lane configuration, and the expanded lanes are expected to be fully functional before the end of 2026. FDOT says those lanes will be open soon. The remaining work is still an inspection job.

Florida Department of Transportation spokesperson Hampton Ray put the count in plain terms to Action News Jax: "You're getting 10 lanes total, 5 lanes in each direction on I-10 between I-295 and I-95." The Nov. 16 report says the project, begun in summer 2020 after persistent delays on the corridor, is finishing slightly ahead of schedule. Officials are conducting final inspections, reviewing the punch list, and verifying that the roadway and pedestrian elements function correctly.

Lanes already in use

Some of the new pavement has been carrying traffic for months. Earlier reporting said two additional eastbound lanes had opened from Cassat Avenue to I-95, and that additional westbound lanes opened over the summer. That account expected the final configuration between I-295 and I-95 within a couple of weeks. The newer report treats the traffic shift as already made and the leftover work as checks, not as another opening announcement.

A finish line that moved

The calendar attached to the job has not held still. In April 2025, Action News Jax reported that FDOT expected the widening completed by the end of 2025, weather permitting. A separate account put the whole project in early 2027, "weather and unforeseen circumstances permitting," at a stated cost of $174.5 million. The Nov. 16 report expects the expanded lanes fully functional before this year is out, and calls the work slightly ahead of schedule. Which timetable that "ahead" is measured against is not spelled out.

Four published prices

The bill has worn more than one number, and the write-ups do not say whether those figures are revisions, different scopes, or something else. Action News Jax has described a $170 million project aimed at adding lanes to the existing interstate. The early-2027 account used $174.5 million. Action News Jax's Nov. 16 report cited $194.3 million. In 2021, The Jaxson described a $176.4 million widening through Jacksonville's Westside. Same corridor, four public price tags, no ledger in these reports that picks a winner.

Under the lanes

The widening was pitched as more than extra asphalt. The Jaxson described it as a project to improve traffic flow, safety and capacity. The work added pedestrian facilities and hardscaping, and it includes a Lane Avenue design embedded in the MSC wall. At the Luna Street pedestrian tunnel, crews have been adding lighting, safety measures and drainage. FDOT is still checking that those pedestrian pieces work. That is the unglamorous half of calling a corridor finished.

Ray has already put a number on the load: "Today, we have over 138,000 drivers on I-10 in this corridor every single day." FDOT expects another 40,000 vehicles a day on the corridor over the next 20 years. He also said I-10 is not expected to see any tolling for the foreseeable future. Five lanes each way is the capacity answer on the table. The forecast says the table is still going to fill up.

The remodel you drive through

Ray did not pretend the multi-year job was painless for people stuck in it. "No one enjoys construction, no one enjoys having their home remodeled, especially while you're living it, and that's basically what construction tends to be." State transportation officials have called the project vital to strengthening Jacksonville's infrastructure for population growth. The completed corridor is supposed to mean less time in traffic, more time with family, and a lift for the local economy.

Those are the aims. The practical fact is smaller: the punch list is still open, the 10-lane layout is what FDOT says this stretch is getting, and nobody at the department is describing a toll booth on the way there.