The Jersey City Municipal Utilities Authority has applied for between $15 million and $18 million in state funding to fix chronic flooding in Country Village, a neighborhood where residents have endured recurring water problems for decades. The application targets a multi-phase stormwater project designed to keep floodwater out of homes and streets by routing it away from the area's overtaxed combined sewer system.
According to Hudson County View, the funding application is currently under review by the New Jersey Infrastructure Bank. The MUA has already taken steps ahead of that decision, including modifying an existing facility to push more stormwater into the Hackensack River, which reduces the amount of water that can contribute to flooding in the neighborhood.
The flooding fits a wider pattern in western Jersey City. A regional flood assessment found that rainfall flooding is a frequent concern in the area because the combined sewer system and limited drainage capacity restrict stormwater handling; it also identified Country Village as a location with recurring flooding and basement problems. The assessment noted that Hurricane Sandy flooded low-lying areas along the Hackensack, including Country Village. The 2022 Resilient Northeastern New Jersey assessment distinguishes these rainfall risks from coastal storm-surge flooding.
A Pump Station and a Three-Phase Plan
The authority has also built a new pump station specifically meant to move stormwater out of the area, the outlet reports. That pump station is central to the broader fix: the full project is set to roll out in three phases, with the first phase prioritizing the section of Country Village farthest from the pump station, where residents have reported the most severe flooding concerns.
The plan's final phase is its most ambitious piece. It calls for constructing a dedicated pipe that would carry stormwater directly to the pump station, bypassing the combined sewer system altogether, per the same report. That bypass is designed to prevent stormwater from overwhelming the sewer infrastructure that has struggled to keep pace with heavy rain in the neighborhood.
Separating stormwater from sewage is an established strategy for reducing pressure on combined systems, though it is a major infrastructure undertaking. The state says Jersey City MUA has completed sewer-separation projects that mitigated flooding by reducing stormwater entering the combined sewer system, and that additional separation and storage work is planned. Paterson has also completed separation projects to reduce flooding. New Jersey’s CSO case studies place the Country Village proposal within a broader effort to manage wet-weather flows across older urban sewer networks.
Permits Done, but NJDEP Sign-Off Still Pending
Required permits for the project have already been completed, but the project is still awaiting final approval from the New Jersey Department of Environmental Protection before it can go out to public bid, the report notes. Once that approval comes through and bidding wraps up, construction can move forward after a contractor is selected.
The state financing process involves both the Infrastructure Bank and the Department of Environmental Protection. The New Jersey Water Bank is a partnership between the two agencies that provides low-cost financing for eligible water infrastructure projects; municipalities and other eligible sponsors apply through the program, and eligibility depends on the project and the sponsor meeting program requirements. The Infrastructure Bank’s program overview describes the financing structure, underscoring that the pending application is part of a formal review rather than a construction award.
Jersey City Mayor James Solomon said the city remains committed to pushing the project ahead, with the final phase meant to build on the improvements already completed to address flooding concerns that have lingered for years. “Country Village residents deserve a lasting solution to the flooding they've dealt with for decades,” Solomon said, according to the outlet's report.
MUA Leadership Frames Flooding as an Ongoing Priority
Jersey City MUA Executive Director John Metro echoed that urgency, saying reducing flooding's impact on Country Village residents remains a priority for the authority. “We are working closely with the city to advance infrastructure improvements that will better manage stormwater, reduce flooding and provide lasting relief for the neighborhood,” Metro said.
With the funding application still pending before the New Jersey Infrastructure Bank and NJDEP approval outstanding, there's no construction timeline yet for Country Village. For now, the completed facility upgrades and pump station represent the first concrete steps toward a fix that residents in the flood-prone neighborhood have waited on for a long time.