LA28's deficit widened to $595 million in 2025, up from $362 million the year before, according to a new tax filing from the private nonprofit planning the 2028 Summer Olympics. The organizing committee's staff nearly tripled over the same period, growing from 185 employees in 2024 to 549 last year, with the current headcount now topping 900. LA28 insists the numbers don't tell the whole story.
A Deficit That Keeps Climbing
The filing, reported by the Los Angeles Times, shows LA28 reported just $42 million in revenue last year against $275.5 million in total expenses. The deficit has grown every year since 2017, per the same report, a trend that predates the pandemic-delayed Tokyo Games and stretches across nearly a decade of planning for Los Angeles's turn hosting the Olympics. LA28 chair Casey Wasserman pushed back on reading the filing as a sign of trouble, saying the report does not reflect what he described as the robust health of the organization's finances.
Wasserman said LA28 has received no public money and has never borrowed money, and that the nonprofit has significant excess cash on hand for current and future expenses. LA28 spokesperson Jacie Prieto Lopez offered a similar explanation, saying the finances are strong and that the deficit reflects timing of revenue recognition rather than an operational or cash shortfall. Under its accounting practices, LA28 cannot recognize sponsorship and ticket revenue until it has completely delivered the services tied to those contracts, the committee says, and it has deferred recognition of more than $1 billion in revenue through 2025 until those obligations are performed.
Tickets, Sponsorships, and a Different Set of Numbers
LA28 says it has more than $2 billion in contracted commercial revenue and has sold more than 6 million tickets, a sales pace the committee says has outpaced the 2024 Paris Olympics at the same point more than 18 months before the Games. By comparison, Paris had sold 5.39 million tickets through its second sales drop in May 2023 and reached 9.5 million tickets in total, the Times reported. LA28 has also said it plans to shift the remaining estimated 10.5 million Olympic tickets to first-come, first-served sales beginning in 2027.
Not every account of LA28's finances lines up. A separate report from the Sports Examiner, describing a different financial statement, put LA28's 2025 loss at $201.127 million, with $167.120 million in declared revenue against $368.247 million in costs — figures that do not match the tax filing's $595 million deficit measure. LA28's overall Games budget was about $7.26 billion. Governing has reported that the 2028 Games budget has grown overall from an initial $5.3 billion to $7.3 billion, citing inflation, added sports, refined venue plans and contract changes.
Executive Pay Draws Scrutiny
The filing shows LA28 chief executive Reynold Hoover was compensated $965,226 in 2025. Chief operating officer John Harper and chief financial officer Karen Sturges each received roughly $720,000 last year, while former chief legal officer Tanja Olano, who left the organization in 2024, was paid about $519,000 in 2025. Former chief external affairs officer Michelle Schwartz, who also departed in 2024, received about $258,000 that year.
Kathryn Carter, who worked at LA28 for five years before stepping down as chief executive in late 2023, received separation payments of nearly $2 million in 2024 and $975,000 in 2025. Wasserman said Carter's long-term payments included earned bonuses and were structured over time because that arrangement was more cost-effective than a single lump-sum payout. Prieto Lopez said the committee's executive compensation is consistent with comparable nonprofit organizations and reflects the scale and complexity of the Games, adding that LA28 consulted industry experts and benchmarked pay against similar organizations.
Outside experts offered a mixed but largely unalarmed read on the pay figures. Victor Matheson, a sports economics professor at College of the Holy Cross, said the salaries did not raise any red flags for excess when compared with other sports executive pay. Wasserman also noted that companies and government agencies doing business with LA28 push hard to get the most money they can out of the nonprofit, and said inflation has made goods and services more expensive than originally projected.
Who Pays if the Games Run Over Budget
Questions about potential public exposure have followed LA28 for months. A report from the Orange County Register described terms under which, if the Games run a deficit after LA28's $270 million contingency fund is exhausted, the city of Los Angeles would be responsible for the next $270 million and California would be on the hook for the following $270 million. Security costs have also drawn separate projections, with the Los Angeles Police Department estimating costs of $3.5 billion to $4 billion and Los Angeles Police Chief Jim McDonnell projecting the figure could reach $4 billion, against an initial federal security allocation of $1 billion.
LA28's highest-paid contractor in 2025 was AECOM, the committee's official venue infrastructure partner, which received $52.9 million for architecture, design, program management and construction management services. The committee has also directed money toward community programs, including a grant of about $37.5 million to the L.A. Department of Recreation and Parks for the PlayLA youth sports program, and $1 million to Airbnb.org for wildfire disaster relief tied to the 2025 Palisades fire. Prieto Lopez said LA28 supported Los Angeles residents after that fire, and Airbnb.org, which provided temporary housing during the housing emergency that followed, received an additional $1 million in housing credits from LA28 during that period.