Two sprawling solar farms taking shape in rural Louisiana have picked up fresh financing as construction pushes toward the finish line. Treaty Oak Clean Energy's Beekman and Hollis Creek projects, spread across Morehouse and Sabine parishes, are part of a 385-megawatt buildout expected to reach commercial operation in the first half of 2027.

According to Construction Review, Treaty Oak secured $430 million in tax equity commitments from RBC Community Investments for the two projects, with Beekman's commitment closing in September 2026 and Hollis Creek's in October 2026. That financing builds on construction funding Treaty Oak announced on January 8, 2026. In that announcement, the company said Beekman's financing had closed November 20, 2025, Hollis Creek's had closed December 19, 2025, and construction had begun on both sites in 2025, as detailed by Treaty Oak Clean Energy.

That January announcement put Beekman's construction financing at $410 million and Hollis Creek's at $399 million, both structured as non-recourse senior secured credit facilities. Treaty Oak said at the time that the two projects together would add 385 MW of new renewable capacity to Louisiana's grid, with commercial operation expected in the first half of 2027.

Two Sites, Two Parishes, One Combined Portfolio

Beekman Solar sits in Morehouse Parish and is planned for 185 MW of capacity across roughly 1,600 acres, while Hollis Creek Solar in Sabine Parish carries a 200 MW capacity spread over about 2,300 acres, according to Data Center Dynamics. Combined, the two sites make up the 385-MW portfolio Treaty Oak has been developing across the state.

Per the same account, Meta is tied to both projects through long-term agreements, but the electricity itself is not delivered directly to Meta facilities. Instead, the energy generated flows into the local grid, while Meta purchases the environmental attributes associated with the facilities. That structure is a common arrangement for corporate clean-energy deals, where a company backs new generation financially and claims the environmental benefits without taking a direct physical feed.

Jobs, Tax Revenue, and Construction Milestones

Treaty Oak said construction on the two projects began in 2025, and the company's January announcement projected approximately 300 jobs during peak construction. Combined, Beekman and Hollis Creek are expected to generate enough clean energy to power approximately 80,000 homes once operational, per Treaty Oak's own figures.

The projects are also projected to generate more than $100 million in state and local tax revenue over their operating lifetimes, money expected to support local services, infrastructure and community investments in Morehouse and Sabine parishes. Federal energy records list both Beekman and Hollis Creek as under construction and more than 50% complete, though those classifications reflect administrative filings rather than live, on-site inspections.

Tax equity financing of the kind Treaty Oak arranged with RBC Community Investments allows developers like Treaty Oak to monetize project tax attributes, including depreciation and investment tax credits, helping fund large-scale builds before the projects start generating revenue of their own. With financing now closed on both fronts and construction well underway, the two Louisiana sites are on track to become part of the state's growing renewable energy footprint by the time they reach commercial operation in 2027.