California’s Department of Water Resources has flunked the Madera subbasin’s groundwater plan again, telling local water managers in a letter dated Thursday that the previously approved plan is now unsatisfactory. The region’s seven groundwater sustainability agencies have six months to fix the problems or risk a harsher rating that could trigger state intervention.

The Nov. 19 letter, reported by SJV Water, says DWR found the agencies still aren’t adequately monitoring subsidence, or land sinking, in the places where it’s actually happening. Regulators also expressed doubt that the current plan will succeed in bringing the region’s aquifers into balance by 2040, the deadline set under the state’s Sustainable Groundwater Management Act.

Madera County Water and Natural Resources Director Stephanie Anagnoson said she was still working through the letter but expects the subsidence concerns can be resolved. “I am a little disappointed, but know that subsidence is a growing edge for both DWR and the Madera Subbasin and that we’ll figure it out,” she said, according to the outlet’s report. Anagnoson added that the plan doesn’t adequately implement guidelines DWR recently released on managing subsidence, but she doesn’t see anything in the state’s findings that can’t be corrected. “I don’t see anything in here that isn’t fixable,” she said.

New State Rules on Sinking Land

DWR’s newly released subsidence guidelines spell out how local agencies must manage their aquifers to prevent further sinking caused by excessive groundwater pumping, per the same account from SJV Water. Water managers across the San Joaquin Valley are now responsible for folding those standards into groundwater plans that in many cases were written and approved years earlier.

The stakes of ignoring subsidence are visible along the Eastside Bypass between Firebaugh and Madera, where excessive pumping caused the land beneath a bridge to sink, according to the report. The concrete posts that once supported the bridge sank along with the ground and had to be replaced.

Not the First Time Madera's Plans Have Been Sent Back

This isn’t the Madera subbasin’s first rejection. State regulators previously kicked back four plans submitted by the same seven groundwater sustainability agencies, giving them 180 days to correct problems tied to protecting domestic wells and ignoring subsidence, according to a separate SJV Water report. At the time, a State Water Resources Control Board analysis estimated that between 895 and 1,399 domestic wells could dry up if groundwater levels fell to the minimum thresholds laid out in those plans, while 184 domestic wells had already gone dry at water levels far higher than those the plans projected.

DWR staff also pushed back on the agencies’ earlier position that subsidence had not harmed infrastructure, requiring them to rethink that stance, the outlet reported.

Madera Isn't Alone in the San Joaquin Valley

Madera’s subbasin is one of several in the region facing scrutiny over subsidence. DWR deemed the neighboring Merced subbasin’s groundwater plan incomplete last month, according to SJV Water. In a related report on Merced, the outlet noted that subsidence there still wasn’t being addressed to the state’s satisfaction, even though DWR said its new subsidence guidelines weren’t a factor in that particular determination. Merced’s subbasin measured 3.8 feet of subsidence between 2015 and 2025, while its plan allows for up to 7.5 feet by the end of 2040, and its three groundwater sustainability agencies have 180 days to address the deficiencies DWR identified. DWR had previously deemed Merced’s plan incomplete back in 2022 before approving a revised version in 2023, warning at the time that unresolved issues could lead to another incomplete or worse finding down the road.

Westlands Water District has faced similar pressure. DWR approved its revised groundwater sustainability plan in August 2023 with additional corrective actions recommended, but according to the Water Education Foundation, state officials have continued raising concerns about ongoing subsidence there and its effects on the California Aqueduct. The foundation reports that ongoing subsidence statewide could shrink the aqueduct’s carrying capacity by nearly 90 percent over the next 17 years.

What Happens If Madera Can't Fix It

SGMA, passed in 2014, required 94 medium- and high-priority groundwater subbasins statewide to form sustainability agencies and develop plans to end excessive pumping by the early 2040s, per the Water Education Foundation. Under the law, DWR is the agency tasked with assessing and evaluating those plans, according to the California Department of Water Resources.

If Madera’s corrections aren’t accepted within the six-month window, the subbasin’s plan could be deemed inadequate, which could lead to a referral to the State Water Resources Control Board, SGMA’s enforcement arm, SJV Water reported. For now, Anagnoson has signaled confidence that the subbasin can avoid that outcome, even as the clock starts on another round of fixes to a plan state regulators have flagged before.