New York City/ Weather & Environment

Maspeth Battery Plant Proposed for 54th Avenue in $80.7M Project

AI Assisted Icon
Published on November 21, 2026
Maspeth Battery Plant Proposed for 54th Avenue in $80.7M Project53-11 54th Ave. — Maspeth Street Scene
Google Street View

A battery energy storage facility is planned for a Maspeth, Queens industrial lot, according to New York City Industrial Development Agency documents. The project, proposed by Soltage Maspeth ESS LLC at 53-11 54th Avenue, is pegged at roughly $80.7 million and would add to a wave of similar facilities popping up across the five boroughs.

The application, detailed in a cost/benefit analysis posted by edc.nyc, describes a 20-megawatt system capable of storing 80 megawatt-hours of energy per day. The facility itself would take up 7,726 square feet on a 25,696-square-foot parcel, a relatively compact footprint for a project of this scale.

The NYCIDA's board adopted a resolution on September 29, 2025, authorizing the applicant to proceed and approving what's known as a straight-lease transaction for financial assistance, according to the agency's own agenda and resolutions document. Soltage Maspeth ESS is described in the resolution as an indirect wholly owned subsidiary of Soltage, LLC, which the agency calls a private, independent power producer that develops solar and energy storage projects.

Tax Breaks and Jobs Tied to the Deal

The cost/benefit analysis estimates the project will generate $3,699,254 in tax exemptions against an expected $4,559,179 in direct and indirect city tax revenue from operations and renovation. The project includes a sales tax exemption and a mortgage recording tax benefit among NYC taxes to be exempted. In exchange, the applicant expects to create six full-time-equivalent jobs.

It's a modest headcount for an eight-figure capital project, but battery storage facilities are generally not labor-intensive once built — the value lies in the equipment's ability to bank electricity for later use.

A Citywide Buildout Already Underway

The Maspeth plant would join a fast-growing local footprint for Soltage. The company announced in September that its 55 Drive facility, its first battery storage system in New York City, had just completed a second full operating season, discharging at full capacity during peak summer demand, per Morningstar. That system is a 4.6 MW / 18.4 MWh asset connected to a Con Edison distribution circuit. The same announcement said six additional city storage projects were under construction, totaling 30 MW / 120 MWh, with another 115 MW / 460 MWh in advanced development.

State Push for More Storage Capacity

New York State is simultaneously ramping up procurement for large-scale storage. On Nov. 12, NYSERDA announced a solicitation for up to 1 gigawatt of bulk energy storage, which Utility Dive described as the second of at least three competitive procurements planned under the state's Energy Storage Roadmap. The state is targeting 6 gigawatts of total energy storage by 2030, including 3 gigawatts of bulk storage, according to Utility Dive.

Notably, the outlet reported that NYSERDA wants at least 30% of that 3-gigawatt bulk storage target located within NYISO Zone J, the zone covering all five boroughs — underscoring why projects like the one proposed for 54th Avenue carry weight beyond their individual size. Separately, Utility Dive reported September awards for eight new bulk energy storage projects and referenced 700 MW of renewables.