Middlesex Judge Weighs Whether Neighbors Missed Deadline to Fight PAX-1 Data Center

AI Assisted Icon
Published on November 15, 2026
Middlesex Judge Weighs Whether Neighbors Missed Deadline to Fight PAX-1 Data CenterSource: Doug Kerr / Wikimedia Commons

A Cumberland County judge heard dueling arguments Friday over whether five Middlesex Township neighbors waited too long to challenge the zoning behind the sprawling PAX-1 data center, but he did not rule from the bench. Judge Matthew Smith took the matter under advisement after lawyers for the project's developers and for the neighbors argued over when, exactly, the clock started ticking on the appeal.

The hearing centered on a technical but consequential question: did the 30-day appeal window open when PPL Electric won approval for Phase 1-A substation plans in March 2025, or when the first data center campus itself got the green light from Middlesex Township supervisors on May 6, 2025? According to PennLive, Carlisle Development Partners argued the earlier substation approval should have triggered the appeal period, meaning the neighbors' challenge came too late to count.

Neighbors' attorney Nathan Wolf pushed back, arguing the substation approval did not make the spot-zoning issue ripe for appeal because the substation is an essential utility service allowed regardless of township zoning. PPL Electric has said the substation is needed for transmission-system reliability and resiliency independent of the data center project. Wolf filed the zoning appeal with the Middlesex Zoning Hearing Board within a week of the May 6 approval of the first data center campus, and the court case followed after that initial township appeal was never acted on.

Five Neighbors, One Overlay District

The challenge is being brought by five Middlesex neighbors, including named plaintiff Kyle Gerber, who argue that the township's data center overlay district amounts to illegal spot zoning. Pennsylvania appellate courts have ruled spot zoning illegal in past cases. Middlesex Township supervisors approved the overlay in May 2025, making data centers a permitted use on land that PennLive's November report described as zoned for residential development and some small neighborhood commercial uses before the change — though PennLive's earlier August report described the same underlying zoning as agricultural and residential.

Gerber told reporters that residents simply want a chance to make their case in court. Wolf has argued that the developers — described as a team of local investors paired with a Virginia-based data center developer, with principal Igal Feibush among them — pressed ahead with site work at their own risk while the zoning dispute remained unresolved.

A Project Without Precedent in Pennsylvania

PAX-1 is proposed as a 16-building data center campus projected to provide 1.3 gigawatts of computing power once complete, which developers say would make it larger than any data center existing in Pennsylvania at the time. PennLive's November report places the site at 700 acres off Country Club Road in Middlesex Township, while WITF has reported the campus spanning 693 acres. The proposed buildings are sited more than 900 feet from the closest Country Club Road residences.

Developers have projected the project will generate $65 million annually in new property tax revenue at full build-out. PennLive's August report noted developers' separate projection of $45 million in annual tax revenue to the school system alone, though the outlet said it could not independently corroborate that figure. On jobs, the November PennLive report cited a developer estimate of 250 permanent positions at full build-out, while WITF reported the developer's website put the number at 500 full-time permanent jobs.

Construction Grinds On Despite Legal Limbo

No vertical construction has begun at the site, though PennLive's report notes site work including grading and other preparatory activity is underway. A notice posted by Middlesex Township on Nov. 9 said contractors would pave portions of Country Club Road later that week and/or the following week. Residents have complained since spring about work hours, blasting effects, and truck traffic tied to the site preparation.

Carlisle Development Partners has argued that halting work with a stay would jeopardize the project and could cause tens of millions of dollars in delay damages, since a stay would stop construction while the case is pending. WITF reported that final approval votes for PAX-1's next two phases are planned for February, though the evidence reviewed does not specify which year those votes would occur.

Pennsylvania's Municipalities Planning Code gives townships broad authority to plan and govern development through zoning, subdivision, and land-development ordinances, according to the Pennsylvania General Assembly. That general authority does not resolve whether Middlesex Township's overlay district itself passes legal muster — a question that now rests with Judge Smith, who has given no indication of when he will rule.