Naples Pours $4.3M Into Rebuilding Two Aging Water Wells Near Golden Gate Estates

AI Assisted Icon
Published on November 25, 2026
Naples Pours $4.3M Into Rebuilding Two Aging Water Wells Near Golden Gate EstatesSource: P. Hughes / Wikimedia Commons

Two of Naples' water wells are getting a multimillion-dollar overhaul after decades of service, with the city moving to replace corroding pipe and outdated equipment before it becomes a bigger problem. City Council approved more than $4.3 million in contracts on November 18 to rebuild Wells 410 and 418, both more than four decades old, as part of a broader push to shore up the aging infrastructure that keeps drinking water flowing to the area.

According to Gulfshore Business, council approved a $3,465,283 construction agreement with Cape Coral-based Tru Spec Mechanical to replace and rebuild the two wells, along with a $530,026.76 contract with Texas-based LJA Engineering for construction contract administration. Council also approved a $365,520 contingency allowance for unforeseen circumstances and amended the fiscal year 2026-27 budget to appropriate $4,360,829.76 from the water-sewer fund's unappropriated fund balance to cover the work, the outlet reported.

The city's own bid documents confirm the physical scope of the job. Per the City of Naples's invitation to bid, the project calls for a new well pad, access drive, stormwater management areas, wellhead, above-ground piping, electrical service and submersible pumps at each site. Well 410 sits on 10th Avenue SE, while Well 418 is located on 16th Avenue NE, both on city-owned parcels, the bid materials state.

Corroded Casing Nearing Its Limit

Naples is replacing 14-inch ductile iron casing, which is vulnerable to groundwater-caused corrosion, per George Yilmaz, the city's assistant city manager for critical infrastructure and public works, as reported by Gulfshore Business. The new 17-inch PVC casing, built to a standard dimension ratio of 16, is expected to extend the wells' lifespan by 40 years, according to the same report.

The pumps are getting an upgrade too. Naples' well pumps currently run at roughly 40 horsepower, but the modernized units will increase to 60 horsepower with variable-frequency drives and added reliability engineering, the outlet reported. The project also includes modernizing programmable logic controllers for real-time sensor monitoring and machinery control, with the new controllers set to integrate with motor-operated valves for full remote operations and visibility.

From Cellular to Starlink

The city currently relies on cellular wireless service for well operations, per Yilmaz, as reported by Gulfshore Business. Naples plans to upgrade well communications to Starlink mobile and stationary service, and the city will consider 800-megahertz radio communications and remote control in the future, the outlet reported. The broader goal, per the same report, is to modernize wells for remote control and a reliable SCADA system.

Security is part of the package as well. New measures at the two wells will include fencing, 24-7 remote monitoring with data logs, and 2K cameras, according to Gulfshore Business, with the city planning to retrofit remaining wells with similar security measures outside the current project. City officials say the wellfield improvements are intended to maintain water production capacity and reduce demand on the Coastal Ridge wellfield.

Decades of Planning Behind the Project

Naples has conducted water supply studies and evaluations over the past 20 years, publishing an Integrated Water Resources Plan in 2008 and updating it in 2022, according to Gulfshore Business. City Council formally adopted the original plan on October 1, 2008, accepting it as a “living document” for developing future water-supply strategies, according to naplesgov.com. That 2008 plan selected what it called Alternative 2, prioritizing aquifer storage and recovery along with Golden Gate Canal water supplemented by stormwater, while aiming to minimize brackish groundwater use if those sources proved successful.

The 2008 plan also projected that the utility service area's population would grow from 68,550 to 90,193 over a 20-year planning period, and it capped use of the existing Coastal Ridge and Golden Gate well fields at 24 million gallons per day, per naplesgov.com. Despite that growth planning, the Integrated Water Resources Plan recommended continued investment in the city's wellfields even though no raw water capacity gaps have been identified through 2040, per Yilmaz, as reported by Gulfshore Business.

A Wellfield Serving Tens of Thousands

Naples operates and maintains 51 potable water supply wells across the Golden Gate and Coastal Ridge wellfields, which draw water from the Lower Tamiami Aquifer, according to Gulfshore Business. The city's primary drinking-water wellfield extends from Randall Curve south to 18th Avenue in Golden Gate Estates, and the water plant itself is located at 1000 Fleischmann Blvd., the outlet reported. Altogether, the system's potable water wells serve about 83,000 people, with the service area covering properties within city limits and portions of Collier County.

The 26-035 bid for Wells 410 and 418 has since moved from solicitation to an executed agreement, according to the city's closed bids listing. With construction and engineering contracts now in place, the project marks one piece of a longer-term effort by Naples to replace infrastructure that has quietly aged well past its original design life while keeping water flowing to residents across the city and surrounding county.