North Platte has not approved a single data center, but interest keeps rolling in: the North Platte Area Chamber and Development Corp. says it has fielded about 18 inquiries since early 2025, even as Limitless North Platte LLC, based in Lehi, Utah, has taken purchase options on two sections of land along Hershey-Dickens Road, six miles south of Interstate 80. At the same time, Gov. Jim Pillen’s statewide task force on data centers has wrapped up its work with a fresh set of recommendations for state lawmakers heading into the 2027 legislative session.
Limitless North Platte LLC, based in Lehi, Utah, filed for a new-load-process power-capacity study with the Nebraska Public Power District on Sept. 18, according to reporting by the Omaha World-Herald. NPPD has said such a study is required before any project that would significantly affect the state’s power capacity can move forward, and the utility estimates the review could take most of 2027 to complete.
Despite the inquiries and land discussions, no formal applications have been filed in Lincoln County. Judy Clark, who holds a six-month permit for a temporary asphalt plant along the same stretch of road, said she and Jason Schultz have fielded plenty of questions and concerns from nearby residents — including one of her very first calls, from someone who mistakenly believed a data center had already been approved. Clark said she currently has no applications before her, and she has also said wind and solar cannot supply enough power for a data center, meaning any rural project would likely need a steadier source such as natural gas.
Asphalt Plant Permit Tied to I-80 Repaving, Not a Data Center
The temporary permit tied to Clark’s site is a table-issued permit that does not require a hearing, and it sits on the east side of Hershey-Dickens Road between Kelly Avenue and Antelope Road — about a mile south of the I-80 exit and five miles north of the sections being eyed for a data center. The permit is connected to Werner Construction Co.’s nearly 10-mile I-80 repaving project, not to any data-center plan. Werner submitted the low bid of $10.83 million among three bids for the Hershey-area work.
Werner plans to use the site to store equipment and aggregate this winter and has a road-haul agreement with the county to restore the property once construction wraps. The highway work is expected to begin in April 2027 and run through October 2027, and the asphalt plant itself will not be moved onto the site until that work actually starts.
Micaela Wuehler, a county commissioner and second vice president of the Nebraska Association of County Officials, served on Pillen’s task force and has been fielding her own round of questions back home. She said many people ask whether a data center has been scheduled for a meeting near them, and she has had to clarify that there are currently no data-center applications pending. Wuehler noted that Nebraska residents can look up the task force’s membership and activities through state resources, which include a statewide interactive map showing the six active data centers currently operating in the state — all located in the Omaha and Lincoln areas except for a MARA Holdings facility in Kearney.
Task Force Finalizes Its Recommendations
Pillen’s panel held three monthly meetings in the fall and adopted four recommendations aimed at shaping how Nebraska handles data-center growth going forward. According to KLKN, the task force was created by Pillen to identify safeguards for the state’s natural resources. The North Platte Bulletin reported that the group was charged with evaluating how data centers affect water supplies, power grids and infrastructure; KLKN reported the group finished its final meeting on Nov. 19. The North Platte Bulletin, meanwhile, reported that the task force voted Friday, Nov. 20, to adopt a resolution formalizing those four recommendations for the upcoming legislative session — accounts that differ on the exact timing of the final action.
The recommendations call for maintaining Nebraska’s existing water-management framework and data-center reporting requirements, protecting public-power ratepayers and system reliability, preserving local control over land-use decisions and community engagement, and clarifying local governments’ authority to negotiate, enter and enforce community benefit agreements. Those agreements would require developers to strike deals with affected communities spelling out benefits during a data center’s operation. Pillen said the decision to approve a data center remains a local one, telling the North Platte Bulletin that the task force’s goal was to help communities make informed decisions. The state has also launched a new Nebraska Data Center Resources Hub covering planning and zoning, water, environmental permitting, energy and infrastructure.
Wuehler said county officials need to press senators to make sure counties have the same authority as cities to negotiate community benefit agreements, since existing Nebraska data centers are not located outside a city government’s zoning jurisdiction. Because those existing centers are within city zoning jurisdictions, they can more easily expand and tie into local infrastructure, including public power systems — raising the stakes for rural counties weighing their own rules before a project ever arrives.
Not Everyone Is Convinced the Task Force Struck the Right Balance
Not every voice at the table was satisfied. Nebraska Public Media reported that a rural Lincoln County resident criticized one task-force meeting as a “love letter” to the data-center industry, arguing that environmental concerns received too little attention. On the other side of the ledger, the outlet also cited figures from the Greater Omaha Chamber’s Heath Mello showing Nebraska’s 41 operating data centers support more than 8,800 jobs and generate $170 million in state and local taxes.
The debate is playing out against a backdrop of rising resource use tied to the industry. An Electric Power Research Institute report found Nebraska is one of seven states where data centers could consume more than 20% of total electricity use by 2030, according to 1011 Now. That same report detailed a proposed Google data center near Lincoln that could require between 1,000 and 3,000 megawatts of power — compared with the city’s summer peak demand of about 800 megawatts — and could potentially come online as soon as 2029, though the station noted it remains unclear how close the project is to becoming reality.
Water use has drawn similar scrutiny. The Nebraska Examiner reported that Google’s disclosed water consumption at its Nebraska data centers jumped from 46.6 million gallons in 2022 to 134.7 million in 2023, and then to roughly 732.1 million gallons in 2025 — enough, the outlet noted, to irrigate between 2,500 and 3,500 acres of central Nebraska cornfields. The Examiner also reported that Meta’s Sarpy County data center withdrew between 26.7 million and 37.5 million gallons annually from 2020 through 2024, and noted that evaporative cooling systems tend to use more water while closed-loop systems tend to use more electricity. By comparison, the six Nebraska data centers reporting water use as of Sept. 30 used a combined 765 million gallons over the prior year, the same station reported.
Those numbers help explain why more than a dozen Nebraska counties have placed moratoriums on new data centers, and why lawmakers in at least a dozen states have introduced bills seeking to pause new construction altogether, according to Nebraska Public Media and 1011 Now. In west-central Nebraska, any rural data center large enough to need its own power source would likely require far more acreage than a typical urban facility — a contrast evident in Google’s roughly 600-acre expansion project near Springfield, south of Omaha, compared with the sprawling land and private power plant a standalone rural project would demand.
Lincoln County’s Other Land Business
Data centers weren’t the only land-use matter before Lincoln County commissioners at their last pre-Thanksgiving meeting Monday. The board passed resolutions granting conservation easements on the McWhas’ 821.5-acre ranch southeast of Jeffrey Reservoir and on 23.45 acres of wetlands within a 153.1-acre tract west of Sutherland Reservoir. The Kirk L. Slack Irrevocable Trust owns the wetland site, while the McWhas own the ranch. The U.S. Natural Resources Conservation Service will hold the wetland easement, while the Nebraska Land Trust will hold the easement on the ranch.
For now, rural Lincoln County’s confirmed data-center interest remains limited to a single location, even as inquiries continue. Wuehler said the time to suggest bills to lawmakers is now; Nebraska senators will convene Jan. 6 for the 110th Legislature’s 90-day session — where new bills can only be introduced during the first 10 legislative days.