Bay Area/ Oakland/ Community & Society

Oakley Breaks Ground on Library Set to Leave Freedom High

AI Assisted Icon
Published on November 17, 2026
Oakley Breaks Ground on Library Set to Leave Freedom HighSource: Mattinbgn / Wikimedia Commons

Oakley officials broke ground Monday at Civic Center Park on a city library and community center meant to give the branch a building of its own. The library still shares space inside Freedom High School, where it has operated from a 3,000-square-foot room since 1999.

City Manager Joshua McMurray expects a grand opening in about a year, an estimate rather than a posted opening date. The Press reported the Nov. 16 ceremony, the contract amendment that let work start this week, and the long argument over how large a standalone library Oakley could actually build.

What the Ceremony Put on the Calendar

The new library and community center is planned next to City Hall, on the Civic Center Park side toward Norcross Lane. McMurray called the groundbreaking a monumental day and said many people had a hand in getting the project there. He put the opening about a year out.

Mayor Hugh Henderson said the community had been promised the facility before Oakley's incorporation. He also said the project had been completed without asking voters to approve additional taxes, a financing claim offered at a ceremony that marked the start of construction, not the end of it.

The site change reaches the high school as well. Moving the public library out is expected to let Freedom reclaim the shared space. Liberty Union High School District Superintendent Denise Rugani said the school will have more room for its own library activities, and that a separate city location should allow expanded hours and more community programs. Henderson called Freedom a great partner.

A Lease That Outlasted Its Term

The wait has a paper trail. Contra Costa County Library dates the Oakley library to 1913 and says it now shares space with Freedom High School after a 1999 agreement put it in that 3,000-square-foot campus room. The Press has described the branch as one of the oldest libraries in the county.

The campus deal was never meant to be permanent in quite this way. Friends of the Oakley Library say Freedom and the county library signed a five-year lease in 1999, extended it through 2010, and have been on a month-to-month lease since July 1, 2010. In 2012 the Friends formed a subcommittee to pursue a standalone downtown library and the money to build it.

The building now underway is at the civic center, beside City Hall, rather than a downtown storefront. The practical trade is the one Rugani described: a public branch with its own hours, and a high school that gets its shared room back.

Fees, Grants and a Smaller Ambition

The path from that subcommittee to a shovel has been a series of smaller authorizations. The Press reported that the city approved a design-build agreement with Woodland Construction Builders in September 2025, and that the council confirmed the agreement at a meeting the week before the groundbreaking coverage. A first amendment in February 2026 covered the design phase.

On Feb. 10, The Press reported, a council amendment authorized up to $1.25 million for detailed design. A second amendment included a request for an additional $1.35 million and allowed construction to begin during the week of Nov. 16.

That additional money was identified as coming from the city's park impact fee account, its public facilities impact fee account, and interest on American Rescue Plan Act funds. The Press also reported that Rep. Josh Harder secured $250,000 for emergency generators. Those are distinct pieces of the funding story, not a published total for the building.

Outside money showed up earlier, in separate reports. The Mercury News reported in February 2025 that the project received a $400,000 grant from the Walnut Creek-based Dean and Margaret Lesher Foundation. In August 2024, ContraCosta.news reported a $250,000 pledge from Supervisor Diane Burgis.

The Plan That Kept Getting Smaller

Earlier concepts were much larger than the library the city later said it could fund. The Press described stakeholders picturing a building of about 25,000 square feet, at roughly $1,000 a square foot, or about $25 million. The city's goal was a 28,000-square-foot, $28 million library. Those were planning figures, not a contract for the project that broke ground Monday.

By August 2024 the public number had come down. ContraCosta.news reported that the city had identified $9.5 million for a library of roughly 9,000 square feet, while still describing that larger 28,000-square-foot, $28 million concept. An August 2024 report framed the bigger aim as comparable to facilities in Contra Costa cities of similar size, without naming the buildings.

Henderson's line about avoiding a new voter-approved tax sits next to that shrinkage. The project funding picture includes impact fees, interest on federal relief funds, a congressional earmark for generators, a foundation grant and a supervisor's pledge, as well as $4 million from the city's general fund, $3 million from its special community projects fund, assumed residual land value and fundraising. None of those recent reports supplies a single current price for the building now under construction.

The Park Layout Changes With It

The library is not the only thing moving at Civic Center Park. The Press reported that the park stage will be shifted closer to the center of the lawn as the new building goes in beside City Hall, toward Norcross Lane.

If McMurray's estimate holds, Oakley would have a permanent civic-center library in about a year, Freedom would get its shared room back, and a branch that has been month-to-month since 2010 would finally have a lease that is not with a high school.