Panola College has put a price ceiling on two new campus buildings and, on one of them, started the work students will eventually walk into. The Matthews Foundation Gateway Center, a planned 25,000-square-foot, two-story facility on the west side of campus near Bird Drive, is under construction. Classes are expected to begin there in fall 2027.
The Board of Trustees set that ceiling at a special-called meeting on May 12, the college said in its campus-expansion announcement. The guaranteed maximum price for the two construction projects is $19,056,506. Fold in a previously approved fiber project and the total guaranteed maximum price is $19,885,425.
A Ceiling, Then the Steel
A guaranteed maximum price is a cap, not a receipt. It tells the college what these jobs are not supposed to exceed. It does not, by itself, say how much will actually be spent, or when either building will be finished. The college has not published a completion date for either project.
The fiber piece is the quieter line in the total. The difference between the two figures is $828,919, the amount tied to infrastructure nobody will pose in front of and everybody will notice if it fails. Architectural design for both facilities is being led by Corgan. Jacobe Brothers Construction is providing construction services.
West Side Training, East Side Degrees
The Gateway Center is planned as the hub for workforce and continuing education, cosmetology, social and behavioral sciences, and additional academic programming. That is the building the college says is already underway, with fall 2027 as the target for classes, according to a later Panola College update.
Across campus, the Center for Innovation and Technology is planned as an almost 19,000-square-foot, two-story facility on the east side, near the Frances B. Ross Music Building. The college intends it to support the future launch of associate degrees in civil, electrical and mechanical engineering, and computer science. Panola's varsity eSports program is also planned to move into a dedicated arena there.
Those are different bets sitting inside one price. One building is aimed at programs people already use to get into a job. The other is aimed at degrees the college has not launched yet, plus a varsity arena. The college has confirmed construction only for the Gateway Center.
The Name Came With a Scholarship
On August 31, the Board of Trustees voted to name the new Gateway Center the Matthews Foundation Gateway Center. The relationship the college documents most specifically is older than the building. In 2018, the Charles C. Matthews Foundation established Panola's only endowed scholarship dedicated specifically to workforce-program students. The college says that scholarship has since supported more than 300 students.
The name on the west-side building is therefore attached, in the college's own account, to a scholarship that has already paid for training rather than to a promise about enrollment. The new facility is the larger, later version of that same workforce emphasis.
The Energy Building That Came First
This is not the college's first recent swing at technical training space. In 2023, the Board of Trustees approved construction of a multi-million-dollar energy building, KTRE reported. The plan called for 32,000 square feet indoors and a 25,000-square-foot outdoor yard, with a welding lab, an engines and compression lab, and shops and classrooms for commercial wiring, electrical and motor control, instrumentation, hydraulics and mechanical work, along with HVAC.
Then-president Greg Powell's enrollment claim was blunt. "This new facility will allow us to triple our enrollment," he said of the energy building and the programs it was meant to serve. That was a forecast attached to a different project. The 2026 record does not repeat the promise, and it does not say whether the earlier building delivered it.
What the current paperwork does establish is narrower, and more useful. The board has capped two buildings and a fiber project at $19,885,425. Corgan is designing both facilities, Jacobe Brothers Construction is building them, and the college expects students in the Gateway Center in fall 2027. Between now and that semester, the number that matters is no longer the vote. It is whether the west-side building is actually ready for class.