Google Street View

Pasadena's Planning Commission is set to decide Wednesday whether to recommend a citywide ban on stand-alone commercial data centers, with narrow exceptions carved out for a handful of college campuses and hospitals. The proposal could require 100-foot setbacks from homes, noise and vibration studies, and screening requirements on any facility that does qualify.

According to Pasadena Now, the city's current zoning code does not specifically define data centers at all, a gap that effectively makes them an unpermitted land use under existing rules. City officials want to close that loophole because, as the outlet reports, ambiguity in the code could let developers classify data centers as ordinary offices or research-and-development space to sidestep scrutiny. The amendments up for consideration Wednesday would give the city council a clear definition to work with and spell out exactly where, if anywhere, the facilities could go.

Only Campuses and Hospitals Would Qualify

Under the draft rules, stand-alone commercial data centers would be prohibited throughout Pasadena. The only path forward would be as a secondary use at traditional college campuses and hospitals located in the city's Public/Semi-Public zoning district, and even then only with city approval.

Pasadena Now's report names the properties that could potentially qualify: the California Institute of Technology, ArtCenter College of Design, Fuller Seminary, Huntington Memorial Hospital and Las Encinas Hospital. Any facility built under the new framework would need a master plan or conditional use permit, and it could not sell commercial data-processing services to outside customers — meaning it would have to serve the host institution rather than function as an independent business. The rules would also draw a line between these restricted data centers and the ordinary server rooms or IT equipment that organizations already use to run their own operations, which would remain untouched.

City Staff See Little Upside, Real Resource Strain

A city staff report concluded that data centers offer Pasadena only limited economic advantages. While the facilities can generate construction jobs and tax revenue, Pasadena's economic development staff identified no significant employment gains or secondary benefits for local businesses tied to data center development here. The report pointed to California's property tax limitations, scarce water resources and Pasadena's largely developed landscape as further reasons the payoff could be thin, per Pasadena Now.

The scale of what's at stake is laid out in the same staff report: a 10,000-square-foot data center could draw as much as 10 megawatts of electricity, roughly the annual consumption of 8,000 households, and consume about 40 acre-feet of water a year, comparable to what 120 households use. Those figures echo a statewide pattern. The California Energy Commission says data centers accounted for roughly 1,000 megawatts, or about 2 percent of California ISO's peak electricity demand, in early 2026. A report from Next 10 and a UC Riverside researcher, covered by CalMatters, found that statewide data center electricity use nearly doubled from 5.5 terawatt-hours in 2019 to 10.8 terawatt-hours in 2023, with demand potentially climbing to 25 terawatt-hours by 2028. The same report estimated on-site water use rose from 1,078 acre-feet to 2,302 acre-feet over that span, and that carbon emissions from the sector nearly doubled too, from 1.2 million to 2.4 million tons — though its authors caution the numbers are estimates built without hard data from the centers themselves.

How Pasadena Got Here

The proposal didn't materialize overnight. Pasadena Water and Power briefed officials in March on how data centers could affect electricity demand and infrastructure, and the following month the city council's Housing, Homelessness and Planning Committee raised concerns that large facilities could strain water and power supplies while delivering limited community benefit. The Planning Commission followed up in July with a study session on potential economic benefits, cooling systems and water consumption before arriving at Wednesday's vote.

Planning staff are recommending the zoning amendments be found exempt from the California Environmental Quality Act, arguing the changes would not authorize any specific development or directly cause physical environmental changes on their own. If the commission endorses the package, it would move to the full city council for consideration.

Neighboring Cities Have Already Drawn Hard Lines

Pasadena isn't the first San Gabriel Valley city to grapple with this. Monterey Park voters banned data centers outright in June, passing Measure NDC with 88 percent support, according to the San Gabriel Valley Tribune. That vote followed months of organizing after a proposed 247,000-square-foot data center drew hundreds of opponents to a January City Council meeting, as reported by the New York Times.

Alhambra adopted its own prohibition in June, and voters affirmed it in November with 83 percent support, Pasadena Now reports. The Tribune's own tally from that same election showed the measure holding a commanding lead — 82.6 percent yes to 17.5 percent no — as of 9:21 a.m. on November 5, though that count had not yet been finalized. Baldwin Park and El Monte have taken a more cautious route, each extending temporary moratoriums while they study potential regulations of their own.

State Rules Arrive in January

Pasadena's local debate is unfolding just as state-level oversight tightens. California lawmakers approved several measures addressing data centers' electricity consumption, water use and environmental impacts, and most of the seven new state laws on the subject are scheduled to take effect January 1, 2027, with several requirements phasing in during 2027 and 2028. Among them, an analysis from law firm Holland & Knight notes that SB 887 will bar data center projects from qualifying for a CEQA categorical exemption on any discretionary approval after that date — a change that could reshape how cities like Pasadena review future proposals even after Wednesday's vote is settled.