Pine Hill Tavern dates its run to October 1976. The rear expansion meant to add restaurant space had a mid-spring opening in its sights. As of April, the parking lot was still waiting on finish work.
According to the tavern's own account, best friends Jay and Harry bought the business together that October. In 2021, two of Jay's children, Dee-Dee and Tim, bought out Harry's interest. Pine Hill Tavern describes that buyout as the point at which the bar became entirely family-owned.
A 50-by-50 Room Out Back
42 Freeway described the addition as more than 2,000 square feet, about 50 by 50 feet, at the back of the building. The design used large garage-style window doors so the tavern could open to the outdoors. Connor Construction of Deptford was identified as the general contractor.
The outline was already public in February 2023. The Courier-Post reported that Pine Hill Tavern Inc. had applied to the Borough of Pine Hill Planning Board for preliminary and final major site plan approval. The proposal then was a 50-by-50-foot addition with a new dining room and bar, an outdoor deck, and a 39-space parking lot. That earlier plan also described solar panels, another bar area, more dining space, and garage doors opening toward a deck.
Thirty-Nine Spaces, Then Fifty-Three
A later plan, in 42 Freeway's account of the project getting underway, called for more than 2,000 square feet of restaurant space and a total of 53 parking spaces. The 39-space figure belongs to the 2023 proposal. The reporting does not show whether the two counts used the same yardstick, so they remain two dated descriptions rather than one official tally.
On paper, the lot got roomier between those accounts. A bigger number in a later plan is not the same thing as a finished stall.
December Start, April Finish Work
The family anticipated opening the addition in mid-spring, barring major weather delays. The April 2026 update said the construction team had arrived the previous December. It also said the lot was not fully completed and still needed finish work.
That is the last detailed public account of where the work stood: a rear room designed to open outward, a family bar nearly five decades into the same origin story, and a parking lot that had not yet gotten its last coat of attention.