Charleston's Board of Architectural Review is scheduled to look Wednesday, Oct. 14, at 4:30 p.m. at revised plans for a 300-key conference hotel on an empty lot at 411 Meeting St. that is now used for parking.
The drawings pair a nine-story lodging building with a two-story conference wing, and they differ enough from a design the board already approved that the project has to come back. The Post and Courier reported the return to review. Live 5 News reported that the revised designs are on the Wednesday, Oct. 14, 4:30 p.m. agenda and will be considered alongside earlier proposals.
A Conference Hotel, Not Just Keys
The Post and Courier describes the lodging as conference-style, with a room count of 300 keys. Plans show restaurants, bars and a separate spa, plus retail on the first floor of the conference wing.
The wing itself is two stories. The hotel building beside it is nine. That is the physical split on the table: a shorter public piece at the ground, and a much taller lodging block over a site that, for now, holds parked cars.
Housing Moved Next Door, on Paper
The redesign also pulls residential construction away from the hotel parcel. The Post and Courier reports that two nine-story housing components would shift to the neighboring property at 82 Mary St., framed as a compromise between Bennett Hospitality and the city.
The unit math does not line up from one account to the next. The Post and Courier says the property was originally approved in 2016 with a condition requiring 159 residential units, later reduced to 100 by the Board of Zoning Appeals in 2022. It reports that a November agreement then provided a compromise to move those 100 units onto 82 Mary St.
ABC News 4, in a Nov. 20, 2025 report, described a different original mandate: 100 housing units and 146 bedrooms alongside the hotel. That account said a new agreement lets the developer build the housing at 82 Mary St. or split the units between Mary Street and 411 Meeting St.
One version clears the homes entirely off Meeting Street. The other leaves a split on the table. The reports do not describe the same requirement or the same placement.
Final Approval, Then a Return Trip
The BAR granted the project final approval in February 2023. Significant design changes require another look, and the 411 Meeting St. project is seeking conceptual, preliminary and final approval on the way back through.
That is a full stack for a file that already had a final sign-off. The revised plans still need board approval before construction can begin. Wednesday, Oct. 14, at 4:30 p.m. is the next scheduled step, not a recorded start of work.
What 300 More Rooms Would Sit Beside
Explore Charleston reported nearly 5,000 hotel rooms on the peninsula in 2024, a figure carried in MyTV Charleston coverage of the housing change.
Winslow Hastie told ABC News 4 the peninsula would have over 8,500 rooms if proposed hotels are built as submitted. The larger number is a pipeline estimate, not a count of rooms already open. It holds only if those projects go up in the form that was filed.
A different hotel, at 657 King St., is headed for a redesign after a mediated settlement ended a legal challenge over height, The Post and Courier reported. That case is separate from 411 Meeting St. It is another Charleston hotel drawing renegotiated after the first round of approvals, on height there and on housing here.
Live 5 News reported that some residents are already asking how the hotel will contribute to the future of the upper peninsula. The Wednesday, Oct. 14, 4:30 p.m. meeting will not reconcile the two housing accounts. The board is being asked whether this version of the Meeting Street design can advance at all.