Rocky River Tests Barrel Chicanes on Northview Road Before $3M RebuildNorthview Rd. & Orchard Grove Rd. — Approximate Planned Crossing With Curb Ramps
Google Street View

Rocky River has lined Northview Road with temporary barrels arranged like future chicanes, giving drivers a preview of the traffic-calming S-curves the city plans to build permanently during a 2027 rebuild. The barrels are expected to stay in place for at least a month while officials gauge how they affect the roadway.

The temporary setup is meant to test a design that calls for four sets of chicanes along Northview Road, according to cleveland.com. The current plan includes two sets between Center Ridge Road and Hilliard Boulevard and two more between Hilliard and Westway Drive. Chicanes are essentially S-curves built into the roadway, designed to force drivers to slow down as they navigate the bends.

City officials say the stretch has earned the attention. Data show about 3,300 vehicles a day travel Northview between Center Ridge and Hilliard, a 25-mph zone where the 85th-percentile speed clocks in at 30 mph and the 95th-percentile speed reaches 32 mph. Between Hilliard and Westway Drive, roughly 2,500 vehicles pass daily, with the 85th-percentile speed also at 30 mph. The segment between Orchard Grove Road and Marion Lane has the highest speeds on the corridor, averaging 26 mph.

Crash History Fuels the Push for Change

The numbers behind the project extend beyond speed readings. Seven crashes were reported on Northview between Hilliard and Center Ridge from November 2023 through October 2026, two of them involving injuries, with five occurring at intersections and most tied to red-light violations, the outlet's report notes. Three more crashes happened at the Hilliard and Northview intersection during that same stretch, including one with an injury.

Rocky River's Director of Public Safety-Service, Rich Snyder, said his office and the police department fielded considerable communications from residents about speeding on Northview. City officials and a consulting engineer identified the road as suitable for traffic calming, even though it never went through the city's formal traffic-calming program — a process residents can still request through the police department.

Police Chief George Lichman described traffic volume on Northview as extremely high and argued that physical changes to the roadway work better than relying on extra patrols. Lichman said physical measures work around the clock, while enforcement is intermittent and may only slow drivers briefly before speeds creep back up.

Residents Weigh In, With Some Pushback

At an October 6 public meeting, the city offered residents a choice between chicanes, speed tables, or a mix of both. The overwhelming majority favored chicanes, per Snyder's account to the outlet. Mayor Pamela Bobst reported that about 40 residents offered strong feedback that day, with many supporting chicanes for both their traffic-calming function and their appearance, while others raised concerns about noise from speed humps, tables and rumble strips.

Feedback has not been uniformly positive since that meeting. Rocky River's reporting notes that resident reaction has been mixed, and some have objected to a proposed raised crosswalk planned for the intersection of Northview Road and Orchard Grove Road. Snyder said resident input is shaping the final number and placement of chicanes, which will follow spacing guidelines from the Ohio Manual of Uniform Traffic Control Devices.

Elsewhere in the region, temporary traffic-calming tools haven't always landed smoothly. In nearby Brooklyn, residents criticized similar temporary chicanes and speed tables as misplaced and noisy, warning they could be damaged by snow plows and weren't actually slowing drivers, according to Citizen Portal, though Brooklyn's mayor said the measures were temporary and engineers would reevaluate placement.

No Changes Planned for Jameston Drive

Rocky River does not plan any traffic calming on Jameston Drive, since that street lacks the high speeds and heavy traffic seen on Northview. Snyder said the chicanes are not expected to interfere with snow plowing or emergency response on Northview itself.

At the Northview Road and Orchard Grove Road intersection, the city plans a crossing with ADA-compliant curb ramps and advance warning signs. Rectangular rapid flashing beacons will be included as an optional item in the bid package, meaning they could be installed during the project or added later depending on cost and resident feedback.

Funding and a Timeline Still Taking Shape

The broader Northview Road and Jameston Drive project folds the chicane work into a larger overhaul that includes replacing aging water mains, sewer repairs and full repaving. The Cleveland Division of Water awarded about $1.4 million toward the effort through its Suburban Water Main Renewal Program, with Rocky River covering the remaining cost from its capital improvement fund. The city says there's no separate line-item cost for traffic calming since that work is folded into the repaving itself.

Construction is scheduled to start in early spring 2027 and wrap by late fall 2027, with water-main work planned for April through July and repaving plus chicane construction running from July through October. Snyder has said the corridor will most likely be limited to one-way traffic for much of the project, and driveway restrictions are expected to be limited, with the city and its contractor notifying affected residents by letter and email. As of publication, the project had not yet been put out to bid, and no contract had gone before city council.

To track whether the barrels are actually changing driver behavior, Rocky River is using traffic management software from Urban SDK, which has partnered with the city and noted an increase in resident complaints about speeding. The city plans to hold another public meeting in December or January to collect resident input and share how the barrel test performed before finalizing the design.