Schuylerville Central School District has a green light and a game plan: most of its long-planned capital improvement project will unfold over the summers of 2027 and 2028, touching everything from parking lots to chemistry labs across the district's buildings. The district says the work can finally move forward after getting the state's blessing and locking in favorable construction bids.
The New York State Education Department approved the capital improvement project and the district completed its bidding process, according to Schuylerville Central School District. Those favorable bids mattered beyond just the bottom line — they allowed the district to move forward with every planned project alternate, rather than trimming scope to fit a budget. The district says the majority of the project will take place during the summers of 2027 and 2028, with some work scheduled during the 2027–2028 school year itself. The district detailed the schedule on November 13, 2026, before it was covered by Saratoga TODAY newspaper.
Summer 2027: Parking Lots, Playgrounds and a Wider Access Road
The first wave of construction, set for summer 2027, will center on parking lot reconstruction alongside a mix of elementary and middle school upgrades. The district's plan includes the first phase of elementary school classroom cabinetry and LED lighting upgrades, improvements to the elementary school gymnasium, construction of a new playground sidewalk, and the widening of the middle school access road, the district says.
Those parking lot improvements aren't just cosmetic repaving — the plan calls for underground conduit and electrical replacements along with milling and paving work. The district's project alternates, made possible by those favorable bids, also include replacing all basketball baskets in the elementary school gymnasium, adding extra LED lighting throughout the elementary school, building a sidewalk connecting the rear elementary hallway to the playground, and widening the middle school's fire apparatus access road.
Keeping Campus Running During the Work
District officials have already mapped out how school operations will adjust around the construction crews. During daytime construction hours in summer 2027, summer school and Extended School Year programs will be the only programs permitted on campus, the district says. Athletic teams, however, will still get access to campus facilities after 4 p.m. on weekdays and throughout weekends during that same stretch.
Beyond the summer push, one piece of the project will spill into the fall. Elementary school locker replacements are scheduled for September through October 2027, and that work is set to be completed during second-shift hours to minimize disruption to the regular school day, per the district's update.
Summer 2028 Turns to the High School and Cafeteria
The second phase of construction, planned for summer 2028, shifts attention to additional elementary classroom cabinetry and LED lighting upgrades, elementary school lobby renovations, cafeteria window replacements, and elementary school entrance improvements. At the high school, the district says work will include renovations to the chemistry and physics classrooms, chemical storage improvements, entrance lobby renovations, and additional entrance improvements.
A Project Years in the Making
The roots of this schedule trace back to May 2025, when Schuylerville voters approved the capital project proposal by a vote of 501 to 129 — a margin the district described as 80 percent. At the time, the district put the estimated cost of the proposal at $10,795,000, and said the project would carry no additional tax impact because its financing was designed to align with the expiration of the district's current bonds.