Sellersburg Locks Down Data Centers With 1,000-Foot Buffer From Homes

AI Assisted Icon
Published on November 24, 2026
Sellersburg Locks Down Data Centers With 1,000-Foot Buffer From HomesData Center Building
Domaintechnik / Unsplash

Sellersburg has approved new zoning regulations for data centers, solar farms, and energy storage facilities, closing a gap in the town's development rules that previously let developers argue these projects could be built in industrial zones without dedicated standards. The town now has two new zoning categories on the books, but as of day one, no land within Sellersburg is actually zoned for either one.

Two New Districts, No Land Zoned Yet

The regulations, reported by WLKY, establish a Solar Energy District and a Data Center District as separate zoning classifications. According to the town's own plain-language guide published by sellersburg.org, no land within the town currently falls into either district, meaning any developer would have to seek rezoning for a specific parcel before building anything. That rezoning path requires applicants to present their case to the zoning planning commission, which then makes a recommendation to the town council, per WLKY. Indiana state statute requires public hearings for zoning changes, and under the new framework every project needs two separate approvals, each with its own public hearing.

Sellersburg Town Manager Charlie Smith said any such facility would have to go through the town's rezoning process and a public process before it could move forward, according to WLKY. Smith said the proposed changes include letters being sent to affected parties, and the town's guide specifies that neighbors within half a mile of a proposed project would get notice by mail. The Sellersburg Town Council holds final authority over these proposed uses, with decisions following recommendations from the planning commission.

Why The Old Rules Fell Short

The gap stemmed from how the town's prior unified development ordinance was written. The existing ordinance permitted commercial solar energy facilities by right in the general agriculture district but did not address data centers or battery storage facilities at all, according to the News and Tribune. That silence on data centers and battery storage is what allowed developers to argue, under the previous ordinance, that such facilities could be built in industrial zones. The Sellersburg Plan Commission responded by voting to recommend creating the solar and data center districts with tight restrictions on potential developments, the paper reported.

The updated draft followed four public input sessions held in August that drew 16 people offering feedback and suggestions about development in town, the News and Tribune reported in earlier coverage. Within Sellersburg town limits, two properties have the capacity to accommodate these kinds of developments, according to WLKY.

Setbacks, Acreage, and Noise Limits

The standards themselves are detailed. Solar farms must cover at least 40 acres, per the town's guide, while data centers must sit on sites of at least 50 acres, with no more than half of that acreage paved or built upon. Data centers must also stay at least 1,000 feet from homes, and the guide is explicit that there are no exceptions to that distance. Noise at the property line is capped at 50 decibels during the day and 45 decibels at night, and water and sewer utilities must confirm in writing that they can serve a proposed data center without reducing service to existing customers.

Sellersburg Town Council President Brad Amos said the town wanted to make clear that residents opposed these kinds of developments and wanted the regulations strengthened, according to WLKY. Both Amos and Smith emphasized that final decisions remain with elected officials and depend on community input. Smith said the process establishes clear standards and eliminates the gray area that previously existed, while the zoning changes are also expected to reduce the likelihood of legal disputes. The new standards apply to large-scale energy storage facilities as well, and town officials say they're meant to protect properties within town limits going forward.

Part of a Statewide Pattern

Sellersburg isn't acting in isolation. As of last month, more than half of Indiana's counties had passed some form of local restriction on data-center development, according to WFYI. By November 20, 36 of the state's 92 counties had moratoriums or bans on data-center projects, per IPM.

Other communities have taken varied paths to similar ends. Madison County's draft ordinance would cap commercial data centers at 40 acres with a maximum power need of 20 megawatts, after the county passed a one-year moratorium in August to give itself time to write the rules, according to Indiana Public Radio. DeKalb County commissioners adopted their own rules following a roughly six-month moratorium, limiting potential data-center sites to 645 acres, per WOWO. Indianapolis created a Data Center Advisory Committee after approving a temporary moratorium on new development through the end of 2027, with a draft ordinance expected for public feedback in June 2027, WFYI reported. Warrick County's new ordinance creates a floating overlay district but does not automatically approve any data center, according to Tristate Homepage, and Dearborn County's planning commission has advanced proposed solar-farm rules that include acreage caps and a minimum three-mile distance between projects, per WCPO.