Greater Birmingham/ Real Estate & Development

Selma's Rangedale Annex Reopens After $6M Tornado Rebuild, Just One Unit Left Empty

AI Assisted Icon
Published on November 23, 2026
Selma's Rangedale Annex Reopens After $6M Tornado Rebuild, Just One Unit Left EmptySelma & Dallas County Chamber — Hosted Annex Ribbon Cutting
Google Street View

Selma Housing Authority marked the completion of a roughly $6 million renovation at Rangedale Annex on November 17, celebrating the full rebuild of a low-income housing complex that the 2023 EF-2 tornado tore through. All 42 units were gutted down to the studs, and officials say residents have already returned, with only one unit still sitting vacant.

A Yearlong Rebuild After Severe Storm Damage

The ribbon-cutting was hosted by the Selma and Dallas County Chamber of Commerce and Tourism Information at the Rangedale Annex property, which is owned by the Selma Housing Authority. The tornado left the complex with severe water damage that led to mold growth throughout the buildings, according to the Selma Times-Journal. That damage ultimately forced every single unit to be fully gutted as part of the renovation, which Steward Construction Company completed over roughly a year and which included a complete rebuild along with new HVAC systems throughout the complex.

Separate reporting from WAKA last fall documented just how extensive the damage was: more than 40 units at Rangedale Annex were damaged by the EF-2 tornado, forcing residents who lived there to relocate to other properties while the complex sat gated off and contractors moved in to begin work. Housing officials told the station at the time that every unit would be completely gutted and renovated, a plan that has now reached completion.

Insurance Dispute Slowed the Start

Before crews could begin the rebuild, the Selma Housing Authority found itself in a dispute with its insurance company over the funding needed for the project, and that dispute delayed the project's start. Despite the setback, officials say the extended timeline ultimately enabled the housing authority to deliver a stronger finished product once work got underway.

Selma Housing Authority President Kennard Randolph said the recovery required patience and persistence, and framed the tornado as a chapter in the city's past rather than a lasting setback. He said the storm is part of Selma's history but will not define its future, according to the Selma Times-Journal. Selma Mayor Johnny Moss III praised Randolph's leadership through the process and said affordable housing is owed to the city's citizens, adding that public-private partnerships help make projects like this one possible.

Residents Are Already Moving Back In

With the renovation complete, residents have returned to Rangedale Annex, and the complex now has only one vacant unit remaining. Selma Housing Authority Chief Operating Officer Cicely Curtis previously told WAKA that fully renovated units mean fewer future headaches for the agency. “Anytime we have units that are completely renovated, you don't have to worry about those extra repairs to it,” she said. Curtis also said the project would help address Selma's ongoing housing shortage.

Darrell Steward, CEO and founder of Steward Construction Company, said he was proud to help bring the project to completion. Lawrence Wofford, a member of the Selma Housing Authority Board of Commissioners, described the natural disaster as something like a divine spanking meant to bring people together, and said the city and its residents had to work together to see the project through. He added that his prayer is for Selma to keep coming together as a city.

A Property With a Documented Up-and-Down Track Record

Rangedale Annex's condition has fluctuated over the years. Federal inspection records compiled by ProPublica show the property underwent at least five physical inspections between 2013 and March 2019, with scores swinging by more than 20 points between the lowest and highest marks recorded in that span. The ProPublica database notes its figures are current only as of March 2019, meaning the newly completed renovation is not reflected in that historical record.