Spokane has issued its 50th residential rebuild permit for homes destroyed in the wildfires that tore through the city on Aug. 1, a milestone city officials say marks real, if slow, progress for hundreds of families still rebuilding their lives. The announcement comes nearly four months after the Old Trails, Fairview and Autumn Lane fires — collectively known as the Spokane Complex Fire — destroyed hundreds of homes and displaced several thousand residents.
A Milestone Four Months in the Making
According to a City of Spokane news release, the city has now issued 50 residential rebuild permits for homes impacted by the fires, with another 18 units currently in plan review. Mayor Lisa Brown framed the number in human terms rather than bureaucratic ones. “Behind each of these 50 permits is a survivor who has faced the difficult reality of losing a home and the long road toward rebuilding,” Brown said, according to the city. Brown also thanked city planning staff for their work on the recovery effort and said that while the process has felt slow to many residents, recovery is happening.
The scale of what the city is working through is considerable. Spokane County Assessor Tom Konis has said the fires destroyed 600 primary buildings, 598 of them residences, according to the Spokane Journal of Business. Demolition, which the city has described as the first step toward reconstruction, has to happen before most rebuilding can begin — and that process has been slowed by required hazardous-waste removal and asbestos surveys on each property.
Demolitions Outpace Rebuilds, For Now
As of the city's latest update, 326 demolition permits had been opened, with 10 still in review, 221 issued, and 95 finaled. The city said nearly 60% of damaged homes within Spokane city limits have now started the demolition permit process. That marks continued movement from earlier in the recovery: six weeks after the fire, the Spokesman-Review reported the city had issued just 68 demolition permits, covering roughly 13% of destroyed properties, and by October the Spokane Journal of Business put the demolition-permit figure at 50% of destroyed properties citywide.
Before any demolition permit can be issued, the city says hazardous-waste removal and an asbestos survey must be completed on the property, and owners must also submit an asbestos Notice of Intent to the Spokane Regional Clean Air Agency. The city said the Environmental Protection Agency has completed hazardous-waste removal for all impacted homes, and Spokane is offering free asbestos surveys to fire-affected owners whose insurance doesn't cover the cost.
Faster Reviews, Lower Fees
City officials say they've worked to speed up what can otherwise be a grinding permitting process. Fire-related permit reviews — both initial submissions and revisions — are now averaging two-day turnarounds, the city said, with a median time of about five days from submittal to acceptance. Spokane Development Services Center staff are reviewing and issuing permits for fire survivors alongside their regular workload serving other residents seeking building permits.
The streamlining builds on steps the city took earlier in the recovery. When Spokane issued its first rebuild permit on Aug. 27 — for a single-family home that reused existing plans from when the structure was originally built in 2023 — the city had already cut its demolition fee to $35 and waived processing and technology fees for owners of wildfire-affected properties, according to the city's earlier announcement. As the Spokesman-Review has noted, Los Angeles County adopted a similar like-for-like rebuilding code after last year's Palisades and Easton fires, allowing homes to use older plans that might not meet current zoning restrictions.
Ripple Effects on Spokane's Housing Market
The fires' fallout is also reshaping Spokane's broader housing picture. The Spokane Journal of Business reported that from July 1 through Sept. 30, Spokane recorded its best leasing quarter in three years, with renters absorbing about 550 apartment units in the third quarter compared with 416 in the same period a year earlier. The outlet has noted that residents who choose not to rebuild may instead enter the existing housing market, adding competition for homes already in short supply.
For now, the city says it remains focused on moving survivors through the permitting pipeline as quickly as possible while keeping required safety steps intact. As The Seattle Times reported, the city says it remains committed to supporting families as they work to rebuild their lives after a summer that upended entire neighborhoods.