Spotsylvania County's Board of Supervisors voted 4-3 to approve the Crossroads Technology Campus, clearing the way for a massive data center development despite residents packing recent meetings to oppose it. The vote came as Stafford County separately moves forward with plans for more data centers nearby, while tax incentives in Spotsylvania and Stafford's low tax rate have drawn scrutiny.
The supervisors who voted in favor were Tim McLaughlin, Lori Hayes, Drew Mullins and Deborah Frazier, while Chris Yakabouski, Jacob Lane and David Goosman voted against the special-use permit, according to WJLA. The Crossroads campus, which would cover 550 acres near existing neighborhoods, has Amazon Web Services as its end-user, according to the Fredericksburg Free Press. The Free Press reported the Crossroads campus at 555 acres; WJLA separately cited a proposed 633-acre data-center project in its account of the county pipeline.
The developer agreed to noise mitigation, generator-emissions standards and setbacks from homes, and promised not to use groundwater for cooling, per the same WJLA report. Supervisor Lori Hayes told the station that 66% of the site would remain forested, though a separate account from the Free Press cited 63% of the project's footprint as preserved open space. The project's attorney projected more than $30 million in annual revenue for the county and said construction would employ 2,000 workers, while the Free Press separately reported the applicant's own narrative forecasting $38 million to $40 million in annual tax revenue at full buildout.
Residents Say the Numbers Don't Add Up
Homeowners told the board they did not want to be surrounded by data centers, raising pointed questions about what the project would mean for daily life. “Will it affect our home prices? Will we be able to sleep at night with the noise? Will our children get asthma from the additional particulates in the air from the generators?” residents asked, per WJLA's reporting.
Kelly Shaeffer, who opposes data centers that would be visible or audible from her home, said she fears losing home value and watching Spotsylvania follow the path of Loudoun County's so-called data center alley. She said the facilities are popping up too quickly for residents to keep pace with the changes. Cindy Staats, meanwhile, described the arrangement bluntly as a sweetheart deal, saying residents were left disappointed by the approval and by project questions that went unanswered.
Those frustrations echoed concerns raised earlier on the day of the Crossroads approval by Safeguard Spotsy, a resident group that released an 80-page report urging supervisors to defer action on the Crossroads application until outstanding questions were resolved, according to FXBG Advance. The group cited a county survey finding that industrial-style development, including data centers, received only about 11% support in the area covered by the Crossroads site. The same report noted that current project narratives now anticipate initial power energization in late 2031, after earlier estimates had pointed to 2026 and 2028.
A Tax Rate Far Below Neighboring Counties
Much of the resident frustration centers on money. Spotsylvania offers Amazon data centers a computer-and-peripherals tax rate of $1.25 per $100 of assessed value, among the lowest in Virginia, according to WJLA's reporting. Those facilities also receive a refund of 60% of generated tax revenue for the first ten years, a 20% refund for the next ten years, and an accelerated depreciation schedule. By contrast, Fairfax County charges $4.57 per $100 of assessed value, Prince William charges $4.50, and Fauquier and Loudoun counties charge $4.15 — roughly three to four times Spotsylvania's rate.
Stafford County shares Spotsylvania's $1.25 rate, and it too is weighing a major project: a developer has proposed four data centers covering more than 1,400 acres off Kings Highway along the Rappahannock River, near George Washington's boyhood home. A resident named Arlene said the proposed data center and substation would tower over her home, and that she was sad and hoped the project would not move forward. The developer's attorney said the project would generate $245 million in total tax revenue if approved, equal to about 20% of Stafford County's total budget, funding schools, local roads and other public services — and noted that county residents' taxes have already risen 57% over the past five years.
Loudoun County Offers a Cautionary Contrast
Loudoun County, which now has more than 230 data centers with roughly 100 more planned, illustrates both sides of the trade-off Spotsylvania and Stafford are navigating. Loudoun Supervisor Kristen Umstattd said data-center tax revenue covers 100% of the county's general fund and 45% of its entire budget, including schools, and she argued Fredericksburg-area localities should raise their own data center tax rates rather than leave money on the table. Loudoun's 2027 budget is projected to bring in $1.3 billion in data-center revenue, representing 40% of the total budget, according to Data Center Dynamics.
But that growth has come with its own backlash. On Tuesday, Loudoun's Board of Supervisors voted 7-1-1 to approve a 12-month pause on processing legislative data-center applications, with Supervisor Umstattd opposed and Supervisor Caleb Kershner abstaining, according to Loudoun Now. Homeowners had asked the board to pause new substations tied to data centers in hopes of slowing both facility growth and high-voltage transmission line construction, though the resolution exempts applications in specialized tax districts and allows substations deemed necessary for grid reliability to still get public hearings. Dominion Energy and NOVEC warned in a county staff report that customers could face higher electricity costs if new substations are denied.
Back in Spotsylvania, the Crossroads approval adds to a county tally that already included eight approved data centers with ten more in the pipeline, including a proposed 633-acre project near the Lee Hill neighborhoods, per WJLA. The county had briefly allowed by-right data-center development in industrial zones before reversing that decision in February, the Free Press reported. The special-use permit approved for Crossroads reportedly carries 57 conditions in total, with 12 aimed specifically at mitigating noise for nearby homeowners.