Evergy wants to build the Buchanan Bluffs Energy Center in southeastern Buchanan County, just off U.S. 169 and Route E, and it has asked regulators to consider a $4 billion natural gas plant for a region the company says is already short on electricity. The Missouri Public Service Commission will decide whether that application is approved.
Monday evening in St. Joseph, residents met the proposal with questions about the ground around the site and the bills that could follow. They raised water, farming, health, noise, light and the process for taking part in the case, News-Press NOW reported. Evergy representatives said the area has an energy deficit and the company has been importing power from other utility providers to make up for it.
A Plant With a State Line Through It
KQ2 has described the proposal as two 710-megawatt natural gas units. One would be dedicated to Kansas customers. The other would serve Missouri customers through Evergy Missouri. News-Press NOW put the combined capacity at 1,420 megawatts.
Buchanan County would host both units, including the one assigned to customers in another state. The water, noise and light people asked about Monday would stay with the host county either way. Electricity can be dedicated across a state line. A gas plant cannot mail its footprint with it.
Chuck Caisley, Evergy's chief customer officer, said the plant would be operational in the spring of 2032 if it is eventually approved. He has described it as supply for customers in Kansas and Missouri, and as added energy for the Kansas City metro. Evergy says growing demand and tighter regional reliability requirements make more power necessary, and that overall customer demand has increased across the board. Caisley has also said regular customers are using more air conditioning and computers and are home more during the day.
Spring 2032 is an estimate tied to an approval that is still ahead. The commission, not the company, has the final word on the Missouri application. The part of Evergy's case that does not wait on that vote is the deficit it says it is already covering with imported power.
Gallons, Farms and a Place in the Docket
Jason Humphrey, an Evergy executive, gave the hearing a water number and a caution. "150 gallons per minute is a conservative estimate," he said of what the proposed plant would use. If that pace held around the clock, the draw would come to 216,000 gallons a day. Residents did not stop at the pump rate. Farming, health, noise and light were in the same set of questions.
Dozens of people attended Monday's hearing to talk about effects on their lives and their electric bills. A Missouri resident asked why the plants are being built. Reporting on the commission's process described two nights of public hearings, not a single evening of comments.
How to participate was part of the complaint. The application moves on a commission calendar. The site, if it is built, would sit just off U.S. 169 and Route E, in a part of Buchanan County where farming was one of the things people came to defend.
Five Customers, and Not on Route E
Geoff Marke, a columnist with the Missouri Office of the Public Counsel, put the proposal in a much smaller circle. "This additional plan is incremental. It's an additional investment to serve five customers," he said. He included Google and Meta data centers near Smithville among those five. Smithville is not southeastern Buchanan County. The loads he named and the ground residents were asking about are different places.
Caisley has said the plant would be needed even without data centers. He has also said it can accommodate some data-center load, that it is not dedicated to or caused by any single data center, and that data centers will pay entirely for the portion of the plant serving them. Coverage of the proposal describes an Evergy agreement with Missouri and Kansas that requires data centers to pay upfront for infrastructure upgrades tied to their share of needed energy.
Cody Boston, affiliated with a Kansas City data-center watchdog group, asked how much of the power would benefit residents rather than large-load users. He said residents should not be asked to pay the bills for massive data centers, and he hopes regulators deny the application. Kansas City neighbors, in coverage of the same fight, have treated the roughly 1,400-megawatt project as supply for data-center demand and have questioned whether that demand is the only reason it is being proposed.
Those are different claims sitting in one case. Marke described an incremental investment for five customers. Caisley described a plant the company says it would want anyway, with room for some of that load and a promise that large users cover their share. Boston asked who actually benefits. The commission is the body that has to decide which of those descriptions the application supports.
What a Rate Case Counts
The bill argument has a paper trail outside this hearing. Utility Dive put the rate equation in plain terms: if sales increase more than costs, customer rates should decline on average. The disputes it examined start when a utility counts one side of that fraction and not the other.
Evergy Missouri Metro included costs for new gas generation to serve data centers in a rate calculation and did not account for the increased sales to those data centers, the publication reported. That is a separate case from Buchanan Bluffs. It is still a concrete example, from Evergy's Missouri operations, of generation cost entering the math while the new sales do not. Current Energy Group's analysis of a Duke Energy proposal found that correcting sales figures could erase 54% of the requested increase, about $1 billion a year.
Nearly 200 data-center companies have signed the Ratepayer Protection Pledge, committing to pay their fair share of costs. A national pledge does not set a Missouri rate, and it does not assign either unit at Buchanan Bluffs. It also does not answer the question Boston asked: how much of the power is for residents, and who is being asked to fund the rest.
Rules Other States Are Already Writing
Colorado has pushed the same argument into a tariff. The Colorado Public Utilities Commission required Xcel Energy, the state's largest electricity provider with 1.6 million customers, to develop a large-load tariff intended to protect retail customers from costs tied to data centers and other high-demand users, The Colorado Sun reported. Xcel's proposal would apply to new customers needing at least 50 megawatts and would charge each applicant a $120,000 fee.
How long those customers stay on the hook is still contested. Xcel is calling for 15-year contracts, commission staff recommended 20 years, and the Data Center Coalition proposed 10. Xcel estimates it will need 2 gigawatts of generating capacity just for data centers by 2030, against total capacity of just over 7 gigawatts. Eight Colorado municipalities and counties have enacted or are considering moratoriums or caps on data centers.
Those are Colorado choices, not a Missouri order. What is in front of this state's commission is whether Evergy's Buchanan County application goes forward at all. If it does, Caisley said the plant will be operational in the spring of 2032. If it does not, the problem Evergy brought to St. Joseph remains the one it already describes in the present tense: a deficit covered by imported power, and a $4 billion project whose named data-center customers, in Marke's account, sit near Smithville rather than on the ground off Route E.