Stantonsburg Cuts Ribbon on New Town Hall, Ending 76-Year Run at Old Building

AI Assisted Icon
Published on November 11, 2026
Stantonsburg Cuts Ribbon on New Town Hall, Ending 76-Year Run at Old BuildingStantonsburg Town Hall — Reported Site of Ribbon-Cutting
Google Street View

Stantonsburg has a new seat of government. Mayor Coley Rhodes cut the ribbon Monday night on the town's new Town Hall and municipal complex at 312 S. Main St., closing the book on a government building the small Wilson County town had used since 1950.

The ceremony marked the end of a four-year effort to replace the aging facility, according to The Wilson Times. Rhodes told the outlet the project took four years to come to fruition, and he called the new complex a center for local government, public participation and community planning. He added that the moment was rare enough to savor, noting the event happens once every 75 years, a nod to how long the previous building served the town since it opened under then-Mayor Nathan Paul Coley in 1950.

To get there, Stantonsburg acquired a former Duke LifePoint building for about $354,000 and converted it into the new municipal home, the Wilson Times reported. The town renovated the structure using a mix of grants, American Rescue Plan Act dollars and funding from the N.C. General Assembly, according to the same report.

What's Inside the Renovated Complex

The new Town Hall includes council chambers built around a dais, along with equipment to livestream and record future Town Council meetings, the newspaper's account states. The complex also features a small history exhibit detailing the town's past, including portraits of every mayor Stantonsburg has had.

Outside the building sits a less conventional addition: an old mule plow that Town Manager Brian Hawley said Rhodes personally donated to the site. Rhodes said he hopes the facility will serve Stantonsburg well into the future, per the Wilson Times account.

A Project Years in the Making

The town's push for a new municipal building dates back to at least December 2024, when Stantonsburg issued a request for proposals for what it called the Town Hall Municipal Building Project, according to a document posted by the Town of Stantonsburg. That proposal called for a complete interior remodel, minor exterior repairs and a plan to consolidate town administration staff and the police department under one roof.

The 2024 document had hoped the project would wrap up by July or August 2025, with the town occupying the property as early as September 2025. The ribbon-cutting ultimately came more than a year after those hoped-for dates, the town's proposal shows. That same document also noted the project was made possible due to two grant appropriations awarded from the NC General Assembly.

Costs Along the Way

A pre-opening report from the Wilson Times put the total project budget at around $850,000 for the building and its renovation, funded through grant money, American Rescue Plan Act dollars and the town's fund balance. Hawley told the paper that unexpected expenses added roughly $58,000 to the job, covering footer installation, roof repairs, termite damage and HVAC issues.

As a point of comparison, Hawley said contractors estimated that building a new 6,000-square-foot facility from scratch on the same site would have cost more than $2 million, the Wilson Times' report noted. That figure was offered as a cost comparison for new construction rather than a reflection of what the renovation itself ultimately totaled.