Suffolk County says it has paid off roughly $7.1 million in claims tied to the former Lawrence Aviation Industries property in Port Jefferson Station, using proceeds from land sales to the MTA and i.on renewables to close out a financial obligation that had cost taxpayers an estimated $700,000 a year. County officials say the settlement ends the county's financial exposure on a site that spent more than two decades on the federal Superfund list.
How the Money Was Divided
According to The South Shore Press, which attributed the information to Suffolk County, the $7.1 million in claims on the former Lawrence Aviation site were paid from the sale proceeds tied to the MTA and i.on renewables deals. The 2023 federal consent decree lists Maryhaven, North Shore Jewish Center and St. Charles Corporation together as claimants in the case. County Executive Ed Romaine said the claims settlement closed a long and complicated chapter in Suffolk County history.
Suffolk County says the claims payments end its financial exposure on the property, and that the land has now been returned to the tax rolls. The site made titanium sheet metal from 1959 until the Lawrence Aviation plant's closure in 2003, and waste from that operation contaminated groundwater with solvents used to clean metal.
MTA's Rocky Path to a Deal
The sale to the Metropolitan Transportation Authority followed years of fits and starts. An earlier deal for the MTA to purchase about 40 acres for $10 collapsed over disputes involving greenway and transportation easements, before New York State signed a law reviving the purchase. The MTA went on to buy the property from the Suffolk County Landbank for $10, with Newsday and Long Island Business News both describing the completed transaction as 46 acres, even though a Suffolk County announcement had described the planned sale as approximately 40 acres.
The MTA has retained the option to build a rail yard serving the Port Jefferson Branch, but Newsday reports there are no current plans or funding for the type of branch improvements that would require a rail yard at the site. The same point is echoed in the Melville Chamber of Commerce account, which states plainly that there are no current plans and no funding for any Port Jefferson Branch work that would need a yard on the property.
The July 2026 law that revived the MTA purchase also protects the Setauket and Port Jefferson Station Greenway trail. Per the Melville Chamber of Commerce, the greenway is protected, and if a rail yard is ever built, the state Department of Transportation has to move the trail rather than close it.
Solar Power Moves In Next Door
Separately, i.on renewables is buying a 40-acre parcel at the site for $5 million, with plans to install solar panels, according to Long Island Business News. Suffolk County has allocated about 36 acres of the property for the solar farm, and the Brookhaven Industrial Development Agency describes a 7.75-megawatt solar array with more than 13,000 panels that would power more than 1,000 homes, per the agency's analysis. Town Supervisor Dan Panico said the solar installation advances clean energy on previously cleared, polluted land, per The South Shore Press.
Decades of Contamination and Cleanup
The EPA added the Lawrence Aviation property to the federal Superfund National Priorities List in 2000, three years before the plant itself closed, leaving behind what Newsday describes as a mile-long toxic plume. In 2009, the EPA supervised the excavation and off-site disposal of 16,000 tons of PCB-contaminated soils, according to the Suffolk County Legislature, and installed groundwater treatment systems that have operated since 2011.
The New York State Department of Environmental Conservation took over the on-site groundwater treatment system in 2021 and the Old Mill Pond groundwater treatment system in 2022. New York State demolished the abandoned factory buildings in 2024, and in March 2025 the EPA removed the land and soils portion of the site from the Superfund list. The groundwater plume, however, remains listed on the Superfund list and under cleanup, with treatment continuing at the site.
Newsday's overall $48.1 million cleanup figure, reported as completed in 2025, underscores the scale of remediation required before any of the land could change hands. A 2017 study referenced by the Suffolk County Legislature valued the site between $15.6 million and $19.2 million under various reuse scenarios, while a subsequent liquidation appraisal put its value at just $4 million.