Texas regulators have signed off on a sweeping expansion of a natural gas-fired power plant near Abilene, authorizing construction of up to 2,582 megawatts of generating capacity to feed one of the largest artificial intelligence data center campuses in the state. The facility, known as ABI-1, is being built by VoltaGrid to supply electricity to Vantage Data Centers' Frontier campus, a 1,200-acre development in Shackelford County planned as part of the Oracle and OpenAI Stargate initiative.
The Texas Commission on Environmental Quality approved VoltaGrid's expansion of the ABI-1 plant, raising its authorized generating capacity from a prior 709 megawatts to the new total, according to Engineering News-Record. The TCEQ technical review explicitly states that the proposed ABI-1 expansion has a total generating capacity of 2,582 megawatts, according to the Texas Commission on Environmental Quality record. VoltaGrid previously held authorization for 210 natural gas engines and can now construct up to 620 engines across 10 independently operating power blocks, each using Jenbacher reciprocating engines, per Engineering News-Record's reporting.
Inside Frontier's Scale and Timeline
Frontier itself spans nearly two square miles near Abilene and is slated to include 10 data centers totaling 3.7 million square feet, with planned critical computing capacity of 1.4 gigawatts, Engineering News-Record reports. The overall project carries a planned cost of $25 billion, while a single data center building within the campus has an estimated construction cost of $950 million and a planned area of 344,796 square feet, with projected completion in August 2027, according to the same outlet. The generating facility is owned and operated separately from the data centers by VoltaGrid, which plans to serve Frontier's electricity needs once built out.
State construction filings identify Kiewit as the design firm for Frontier's data center buildings, though Kiewit's role, if any, in VoltaGrid's separate generating facility has not been established, Engineering News-Record notes. The outlet also reports that the identities of contractors building the power plant itself, as well as contractors for gas pipelines, electrical distribution and data-center connections, remain unestablished in regulatory records. Scott Gromer, CEO of Mesa Power Solutions, told the publication that his company's typical scope on such projects begins where gas reaches its equipment and ends at the electrical switchgear; Mesa is not involved in the Frontier project.
Engine Configuration and Emissions Controls
VoltaGrid's engine configuration includes 250 Jenbacher J620 engines rated at 3.22 megawatts each and 370 Jenbacher J624 engines rated at 4.80 megawatts each, according to Engineering News-Record. The company's QPAC modular assemblies can accommodate up to four J620 engines or five J624 engines, and engine manufacturer INNIO describes the five-engine J624 configuration as a roughly 25-megawatt unit designed for rapid deployment and incremental data center power expansion, per the same report. Supporting infrastructure planned for the site includes 60 natural gas-fired fuel heaters, 20 diesel-powered black-start engines and four bulk urea storage tanks, with each generating block also slated to include lubricating-oil storage and associated fuel and electrical equipment.
VoltaGrid's permit requires selective catalytic reduction systems to control nitrogen oxide emissions and oxidation catalysts to reduce carbon monoxide and volatile organic compounds, Engineering News-Record reports. A TCEQ technical review projects potential annual emissions of approximately 10.63 million tons of carbon dioxide equivalent, while the permit allows annual nitrogen oxide emissions of approximately 570 tons and annual formaldehyde emissions of 372 tons. These figures represent modeled or permitted emissions rather than measured pollution, according to the same reporting, and regulatory records have not established how many engines have actually been installed or commissioned, or when additional generating blocks will enter service.
A Pause, Then a Resumption
The approval comes after Governor Greg Abbott imposed a statewide permitting pause in September, with TCEQ having issued a preliminary approval notice for ABI-1 on Sept. 22. Environmental watchdog groups examining the records have said it remains unclear whether the ABI-1 application was suspended during that pause, per Engineering News-Record. Texas resumed data center permitting on Nov. 13, and VoltaGrid must still submit an initial Title V operating-permit application before beginning operations.
The resumption followed a broader review: ERCOT told Texas electricity regulators on Nov. 5 that it had received responses from 93% of 465 projects statewide, information the grid operator said was sufficient for a statistically meaningful analysis, according to the Texas Tribune. ERCOT officials plan to present full findings to the Public Utility Commission of Texas on Dec. 10 and discuss them at the commission's open meeting on Dec. 17, the Tribune reports.
Legal Fight Over a Separate San Antonio Project
VoltaGrid and Vantage already face legal scrutiny elsewhere in Texas, though not over Frontier. The Environmental Integrity Project, Sierra Club and Public Citizen filed a Clean Air Act citizen-enforcement action against Vantage entities and VoltaGrid in September over gas-fired facilities serving two San Antonio data-center campuses, according to the groups' court filing. The suit alleges the companies used permits intended for smaller pollution sources instead of the major-source authorizations federal law requires, and that Vantage operated the Rogers Road site's diesel backup generators as a primary power source despite their limited emergency authorization.
“Vantage and VoltaGrid want to come into this Texas neighborhood and dump thousands of tons of air pollutants into an already smoggy community—and they want to do it without the proper permits or even hearing what impacted people have to say,” said Josh Smith, an attorney involved in the case. The Frontier development near Abilene is not part of that lawsuit, Engineering News-Record notes. The two San Antonio plants named in the suit collectively have a capacity of 405 megawatts, and the campus they serve includes 151 backup diesel generators with a combined 455 megawatts of generation capacity, according to the San Antonio Express-News. Environmental groups estimated those two plants could emit 5,600 tons of nitrogen oxides and 323 tons of volatile organic compounds annually, the paper reported — allegations that remain contested in the pending litigation rather than established findings.
Part of a Much Bigger Texas Buildout
ABI-1's expansion fits into a wider surge of behind-the-meter gas power tied to data centers nationwide. As of October 2026, developers had announced plans for more than 100 such plants at U.S. facilities, with planned capacity exceeding 115 gigawatts, according to Cleanview data cited by MIT Technology Review. Only 4.9 gigawatts of that pipeline is currently operating, with another 15.8 gigawatts under construction, the outlet reports. BloombergNEF has estimated that if every planned plant gets built, they could emit 345 million metric tons of carbon dioxide equivalent annually by 2035 — 152 million metric tons more than if those same data centers drew power from the U.S. grid instead.
“The biggest motivator for on-site power right now from data centers is speed,” BloombergNEF's Musfika Mishi told the outlet. Texas's data-center buildout also includes Oracle's existing Abilene campus. Oracle told investors in September that six of the eight buildings at its existing Abilene campus had been delivered, representing an estimated 618 megawatts according to Epoch AI, with the remaining two buildings estimated to have come online around Nov. 1, though Oracle has not confirmed that timeline, per OilPrice.com.