Texas Water Board Staff Recommend $580M for Houston, Laredo, 16 Other Big SystemsTexas Water Development Board — Site Of Grant Recommendation Meeting
Google Street View

Texas Water Development Board staff have recommended $579,911,984 in one-time state grants for 18 of the state's largest water systems, with Houston in line for over $50 million to replace aging pipes and Laredo set to receive $35 million for the same purpose. The recommendation goes before the board at its meeting in Austin on Thursday, Dec. 3.

Houston's Pipes, Laredo's Lines

According to The Texas Dispatch, Houston's recommended $50,430,010 would replace about 106,000 feet of aging water lines across the Second Ward, Independence Heights–Douglas Heights and Midtown. Laredo's recommended $35 million, meanwhile, would replace roughly 32,067 feet of cast-iron and concrete lines installed more than 50 years ago, the outlet reports.

The money comes from House Bill 500, which the Texas Legislature passed in 2025, setting aside $1.038 billion for the Water Supply and Infrastructure Grants program. The agency split $875 million of that appropriation into five groups based on how many people each water system serves, per the same report. Staff's recommendation covers only the two largest population groups — systems serving more than 1 million people, allotted $400 million with a $55 million cap per project, and those serving 150,001 to 1 million people, allotted $220 million with a $35 million cap.

Who Gets the Maximum Grants

Eight extra-large systems would receive a combined $303,753,128, and ten large systems would receive $276,158,856, the staff recommendation shows. Four extra-large recipients — the Edwards Aquifer Authority, Fort Worth, the North Texas Municipal Water District and the Tarrant Regional Water District — would each get the full $55 million maximum. Seven large systems, including Laredo, Corpus Christi, Arlington, Denton, Garland, the Upper Trinity Regional Water District and the North Harris County Regional Water Authority, would each receive the $35 million cap allowed for their group.

Because extra-large systems did not request the full $400 million allotted to their group, staff proposed shifting $56,158,856 of that leftover money to the large-system group, leaving $40,088,016 unspent among extra-large applicants, the article notes. The Edwards Aquifer Authority's recommended $55 million would go toward buying an estimated 3,000 to 4,000 acre-feet of permanent groundwater rights for the aquifer that supplies San Antonio.

Smaller Towns Still Waiting

Smaller cities and rural utilities will have to wait for a later board vote on the remaining $368,576,986 set aside for medium, small and extra-small systems, according to the same source. Staff recommendations for those groups will come at a future meeting once the review process for those applicants is complete.

The scale of demand for the program has been striking. The Texas Dispatch reported in September that $6.9 billion in grant requests were competing for roughly $1 billion in available grants. The Texas Dispatch's account of the Dec. 3 recommendation put the figure at 695 applications seeking more than $7 billion by the July 30 deadline, while a separate Texas Dispatch report on the program's September update cited 676 on-time applications requesting $6,901,946,826, plus 10 late applications deemed ineligible.

Every recommended grant, if approved, must close by May 1, 2027, and all money must be spent by Aug. 31, 2031, per the staff recommendation. The three-member Texas Water Development Board, chaired by L'Oreal Stepney, takes up the proposal at its 9:30 a.m. meeting Thursday in Austin.

Why Houston's Pipes Matter So Much

The push to fix aging infrastructure follows years of documented losses. In 2023, Houston lost 31.8 billion gallons of water to leaks, compared with roughly 19.5 billion gallons lost by the San Antonio Water System and 7.1 billion gallons lost by the City of Austin's water and wastewater utility, according to Houston Public Media. Houston Water has presented a plan to raise its annual pipe replacement rate from 0.06% in 2023 up to 6%, after officials said a 2% rate is needed just to maintain a 50-year pipeline lifespan. A preliminary study cited by the station found that replacing 6% of the city's most vulnerable pipes could cut leaks by more than half and save enough water to supply 160,000 households.

The Dec. 3 recommendation is not the program's first round of awards. The Texas Water Development Board approved $69,511,030 in grants in September for Rio Grande Valley canal lining and conversion projects, with the 17 approved projects expected to conserve nearly 44,000 acre-feet of water annually, according to a Texas Water Development Board press release. Separately, advocacy group Texas Living Waters has discussed the grant program in its analysis. The Texas Water Development Board describes itself on its program page as the agency that plans and finances the state's water supply, and confirms that HB 500 appropriated $1,038,000,000 from the general revenue fund for the grant program.