For Smithfield Road work connected to the new George T. Nasuti Elementary School, Woonsocket faces two separate expenses: $282,000 for engineering and an estimated $1.2 million to $1.5 million for construction. The engineering proposal is the immediate funding question; a construction funding source has not been confirmed, according to The Valley Breeze’s report on the Nov. 9 City Council meeting.
The bid schedule is tied to the school opening
Public Works Director Steven D’Agostino said the city is expected to make roadway improvements under state transportation requirements related to traffic from the school. He said the city was aiming to put the work out to bid by spring, allowing time for construction before the school’s planned September 2027 opening. The Valley Breeze reported that D’Agostino relayed a state Department of Transportation warning that the project could be stopped if a bid was not in place.
Engineering money would leave construction unfunded
Mayor Chris Beauchamp proposed using the City Capital Fund to pay the engineering bill. The fund has $602,000, but it cannot cover both engineering and construction. The engineering work includes preparing and issuing the bid, evaluating bidders, overseeing the project and completing state sign-off requirements, The Valley Breeze reported.
Beauchamp said he had requested congressional district spending, including through the White House, but that support was not assured. He also raised the possibility of funding from the Rhode Island Department of Education, while noting there was no written commitment. D’Agostino said he hoped requests and state delegates might help pay construction costs, according to The Valley Breeze.
The city may start with temporary traffic measures
If full construction funding is not available, Beauchamp said the city could install temporary traffic lights and striping first, with milling and paving deferred until money is secured. He said the school could open with that temporary work in place, though it would not be ideal, The Valley Breeze reported.
The school project prompted the road obligation, and Beauchamp said the Woonsocket School Department knew upgrades would be required. An earlier traffic study presented to the council warned that the new school could push the nearby intersection toward failure during morning and afternoon peak periods, according to a separate Valley Breeze report. That report said D’Amico Engineering had recommended about $2 million in upgrades; D’Agostino had proposed a less costly approach involving milling and repaving, restriping and moving an existing exit slightly to the left. The reporting cited here does not establish whether that earlier recommendation and the current construction estimate cover the same work.