IU Health’s massive new hospital complex on the north edge of downtown Indianapolis has officially cleared the halfway mark, with project leaders saying construction is roughly 60% complete and still on schedule. The 44-acre, $4.3 billion campus will merge IU Health’s two downtown adult hospitals into one modern site that is expected to begin seeing patients in late 2027.

In an update today, the Indianapolis Business Journal reported that officials described steady momentum across the property and cast the project as one of the largest construction efforts in Indiana history, quoting IU Health design and construction leaders on the latest milestones.

What the campus will include

The new downtown campus is anchored by three 16-story patient towers that will house 864 inpatient rooms and about 50 operating rooms, along with a sizable outpatient footprint. The plan also calls for a support building, parking, and a central utility plant to keep the whole operation humming.

The development will further feature a large medical education and research building for the IU School of Medicine, plus ground-floor retail lining Senate Avenue so the complex does not feel like a closed-off medical bunker. According to Construction Owners, the project is expected to top 2.5 million square feet. HFM Magazine reports that the site is being built with unusually large power capacity to handle future technology demands that are likely to grow over the coming decades.

Budget and timeline

Per the 2025 annual report from IU Health, the hospital remains on track to serve its first patient in the fourth quarter of 2027. The health system’s board recently signed off on an additional $450 million for the project to help offset inflation and supply-chain pressures that have hit large construction timelines across the country.

The report frames the downtown campus as a cornerstone of IU Health’s clinical, academic, and research strategy in central Indiana, positioning the complex as a hub for both day-to-day patient care and long-term medical innovation.

Progress on the ground and traffic

Local coverage from September 2025 put structural work at about 45% complete as crews wrapped major concrete and framing milestones across the site. Since then, the skyline-facing steel has steadily filled in.

WRTV has tracked both construction progress and the traffic headaches that come with it, including periodic lane closures and detours on Capitol Avenue tied to utility and street work. The station has rolled out regular photo and video updates from inside the fence line, while its traffic coverage has detailed the temporary closures that have reshaped nearby commuting patterns.

Why it matters for Indy

IU Health’s decision to consolidate University and Methodist hospitals into a single downtown campus is designed to cut duplicate services and trim operating costs, with estimates in local coverage pegging those savings at around $50 million a year. The move is meant to be as much about long-term efficiency as it is about shiny new facilities.

According to IU Health, the project is also tied to community investments and workforce programs, including funding and training efforts highlighted in the system’s annual report.

Over the next 18 months, work on site is expected to shift from heavy structural tasks to enclosure and interior build-out. For neighbors near 16th Street and Capitol Avenue, the towering cranes and big concrete pours may be fading, but they can expect a steady parade of crews handling facade glazing, landscaping, and retail build-outs as the campus moves into systems testing and final outfitting ahead of its planned opening.